1781 E 113TH ST 90059

Certificate Information: 1781 E 113TH ST 90059

Application / Permit
21016-10000-06047
Plan Check / Job No.
B21LA04303
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) SFD. DEMO (E) NON-BEARING PARTITION WALLS, REMODEL KITCHEN AND BATHROOMS AND REMOVE/REPLACE DOORS AND WINDOWS. ALL WORK PER TYPE V SHEET.
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
Permit Finaled on 1/3/2022

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 3/15/2021 FARSHAD ALIMOHAMADI
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 6/1/2021 APPLICANT
Permit Finaled 1/3/2022 EUGENE CASSIDY

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Gmf Construction And Development Inc; Lic. No.: 1037945-B 34145 PCH      DANA POINT, CA 92629

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/1/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 6/1/2021 Corrections Issued EUGENE CASSIDY
HVAC-Rough 6/1/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/1/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 6/7/2021 Corrections Issued JOHN KLARIN
HVAC-Rough 6/8/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 6/8/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 6/10/2021 Approved EUGENE CASSIDY
HVAC-Rough 6/10/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 6/10/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/14/2021 Approved CALEB MEISTER
Insulation 6/14/2021 Corrections Issued CALEB MEISTER
Drywall Nailing 6/18/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 7/1/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Shower Pan 7/1/2021 Corrections Issued JOAQUIN GREENOUGH
Insulation 7/7/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 7/7/2021 Partial Approval JESUS RODRIGUEZ
Shower Pan 7/7/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/22/2021 Approved EUGENE CASSIDY
Final 11/23/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 11/23/2021 Approved EUGENE CASSIDY
Final 12/15/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Not Ready JOHN KLARIN
Final 12/21/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Not Ready EUGENE CASSIDY
Final 12/29/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/29/2021 SGSOV Approved EUGENE CASSIDY
Gas Test 12/30/2021 Approved EUGENE CASSIDY
Final 1/3/2022 Permit Finaled EUGENE CASSIDY