15643 W SHERMAN WAY 91406
Certificate Information: 15643 W SHERMAN WAY 91406
- Application / Permit
- 21016-10000-05928
- Plan Check / Job No.
- B21LA04198
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- PROPOSED MODIFICATION TO (E) WIRELESS TELECOMMUNITCATIONS SITE BY 1. REPLACE (4) AIR21 WITH (4) AIR6449 B41 (L2500+N2500) 2. MOVE GSM TO AIR32 B2A AND MIX MODE L19 1ST CARRIER/GSM - USE EXISTING FIBERS 3. ADD (4) 4415 B25 CONNECT TO OCTO AND CONFIGURE L19 2ND CARRIERE/U19 MIX MODE 4. ADD (1) ADDITIONAL BB6630 FOR LET AND USE EXISTING BB6630 FOR LTE 5. ADD (1) NEW ENCLOSURE 6160 SITE SUPPORT CABINET AND (1) B160 BATTERY CABINET 6. ADD (2) 226630 INSIDE NEW ENCLOSURE 3160 CABINET FOR LTE 2500 7. ADD (1) BB6648 FOR NR2500 INSIDE 6160 8. ADD (4) 6X12 HCS (30M 6AWG, 40M, 6AWG, 40M 6AWG) FOR AIR6449S, 4415S - 1 PER SECTOR 9. ADD (2) VOLTAGE BOOSTER PSU4813S FOR AIR6449 HCSS.
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- Issued on 12/1/2021
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2021 | CELESTE MORRIS |
| Corrections Issued | 3/11/2021 | CELESTE MORRIS |
| Plan Check Approved | 5/25/2021 | SINA KHOSRAVI |
| Issued | 12/1/2021 | APPLICANT |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
Permit Application Clearance Information
| Plan Approval | Cleared | 5/20/2021 | ANTONIO ISAIA |
| ZA Case | Cleared | 5/20/2021 | ANTONIO ISAIA |
| ZA Case | Cleared | 5/20/2021 | ANTONIO ISAIA |
Contact Information
| Contractor | Telcom Engineering Group Llc; Lic. No.: 1075291-A | 473 US HWY 46 CLIFTON, NJ 07011 |
| Engineer | O'Sullivan,, Sean Michael; Lic. No.: C84392 | 25663 VIEW POINTE LAKE FOREST, CA 92630 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 2/3/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 2/3/2022 | Not Ready for Inspection | JEFFREY FULTON |