3415 N VERDUGO ROAD 90065

Certificate Information: 3415 N VERDUGO ROAD 90065

Application / Permit
21016-10000-05924
Plan Check / Job No.
B21LA04192
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR RENOVATION TO ADD 1 BATHROOM. NO ADDED SQFT.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
Permit Finaled on 8/30/2022

Permit Application Status History

Submitted 3/9/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 LUKE GONZALES
Corrections Issued 3/10/2021 LUKE GONZALES
Building Plans Picked Up 3/11/2021 APPLICANT
Applicant returned to address corrections 4/21/2021 ADAM HEGAZI
Plan Check Approved 4/28/2021 ADAM HEGAZI
Issued 5/11/2021 APPLICANT
Permit Finaled 8/30/2022 HAMIK HARTOUNIAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/5/2021 PATRICK MISCHLICH
Supp. Use District POD/CDO/TDO Cleared 4/9/2021 ADRINEH MELKONIAN
ZI Cleared 4/9/2021 ADRINEH MELKONIAN
"Q" conditions Cleared 4/12/2021 MINDY NGUYEN
Eng Process Fee Ord 176,300 Cleared 4/12/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 4/12/2021 THOMAS LANG
ZA Case Cleared 4/12/2021 MINDY NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Hyams,, Steven Frederick; Lic. No.: C36629 2982 VILLA CATALONIA CIR      CORONA, CA 92881

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/13/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/18/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/27/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/13/2021 Not Ready for Inspection CHARLES BOGHOSKHAN
ELECTRICAL-Rough 7/14/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/14/2021 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/9/2021 Approved HAMIK HARTOUNIAN
Insulation 8/9/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 8/9/2021 Approved HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 8/24/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/25/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/2/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 9/2/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/10/2021 No Access for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/28/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/28/2021 Approved HAMIK HARTOUNIAN
Insulation 9/28/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/12/2021 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/12/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/22/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/28/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 8/9/2022 Approved HAMIK HARTOUNIAN
Final 8/9/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 8/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 8/9/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 8/9/2022 Approved HAMIK HARTOUNIAN
Final 8/19/2022 Partial Approval KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved KATHRYN BUTTERWORTH
Final 8/30/2022 Permit Finaled HAMIK HARTOUNIAN