1190 S WINDSOR BLVD 90019
Certificate Information: 1190 S WINDSOR BLVD 90019
- Application / Permit
- 21016-10000-05838
- Plan Check / Job No.
- B21LA04141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 12X18 SINGLE CAR GARAGE TO NEW ADU 216 S.F. TOTAL
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | JOE VO |
| Corrections Issued | 3/8/2021 | JOE VO |
| Plan Check Approved | 3/17/2021 | JOE VO |
| Issued | 3/24/2021 | APPLICANT |
| CofO in Progress | 9/9/2022 | STUART CHAPMAN |
| No Progress | 9/9/2022 | STUART CHAPMAN |
| CofO in Progress | 10/31/2022 | STUART CHAPMAN |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/9/2021 | ROSA SILVA |
| HPOZ | Cleared | 3/17/2021 | AMANDA KAINER |
| Historic monument | Cleared | 3/17/2021 | AMANDA KAINER |
Contact Information
| Contractor | All In One Construction; Lic. No.: 674782-B | 1056 CYPRESS AVENUE #H LA HABRA, CA 90631 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/6/2021 | Partial Approval | RUBEN SALAS |
| Pre-Inspection | 4/7/2021 | Approved | STUART CHAPMAN |
| Sewer | 4/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/19/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/21/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 5/7/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 5/17/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/1/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 7/1/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/1/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 7/1/2021 | Approved | JOSEPH MCGARRY |
| Wood Frame | 7/1/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 7/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 7/13/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 7/15/2021 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 8/3/2021 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 8/3/2021 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 8/11/2021 | Approved | STUART CHAPMAN |
| Insulation | 8/11/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/9/2021 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 9/9/2021 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/9/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/28/2021 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 10/19/2021 | Approved | STUART CHAPMAN |
| HVAC-Final | 2/8/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/18/2022 | Conditional Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 4/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/18/2022 | Corrections Issued | STUART CHAPMAN |
| METHANE-Final | 4/18/2022 | Approved | STUART CHAPMAN |
| METHANE-Rough | 4/18/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 4/18/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 7/25/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 7/28/2022 | Approved | STUART CHAPMAN |
| Final | 7/28/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Final | 9/8/2022 | Approved | STUART CHAPMAN |
| Final | 9/8/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 9/8/2022 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 9/8/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 10/6/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 10/28/2022 | OK to Issue CofO | STUART CHAPMAN |