17449-17451 W MARTHA ST 91316
Certificate Information: 17449-17451 W MARTHA ST 91316
- Application / Permit
- 21016-10000-05646
- Plan Check / Job No.
- B21LA03956
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** CONVERT EXISTING SECOND FLOOR IN A 2-STORY SINGLE FAMILY INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | MICHAEL LOPEZ |
| Corrections Issued | 3/15/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 3/23/2021 | WING SUEN |
| Plan Check Approved | 4/6/2021 | MICHAEL LOPEZ |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 2/22/2022 | SEAN HAUPT |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
| CofO Issued | 3/6/2022 | MICHAEL SMITH |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hold | Cleared | 3/16/2021 | JASON SHEETS |
| Address approval | Cleared | 3/17/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/17/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/20/2021 | Corrections Issued | DAVID SANDOVAL |
| Pre-Inspection | 7/22/2021 | Partial Inspection | STEVEN BACK |
| Pre-Inspection | 7/28/2021 | Partial Inspection | STEVEN BACK |
| Footing/Foundation/Slab | 8/26/2021 | Approved | STEVEN BACK |
| Rough-Elec/Plmb/HVAC | 9/17/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | STEVEN BACK |
| Insulation | 10/6/2021 | Approved | STEVEN BACK |
| MERV13>=Rough | 10/6/2021 | Approved | STEVEN BACK |
| Shower Pan | 10/6/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 10/15/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/15/2021 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/26/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 1/26/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 1/26/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 1/26/2022 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 2/15/2022 | Approved | SEAN HAUPT |
| Final | 2/15/2022 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 2/15/2022 | Partial Approval | SEAN HAUPT |
| MERV13>=Final | 2/15/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 2/15/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 2/15/2022 | Approved | SEAN HAUPT |
| Final | 2/22/2022 | OK to Issue CofO | SEAN HAUPT |