722 S BROADWAY Floor 7 &8 90014
Certificate Information: 722 S BROADWAY Floor 7 &8 90014
- Application / Permit
- 21016-10000-05644
- Plan Check / Job No.
- B21LA03954
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR NON-STRUCTURAL DEMOLITION AND OFFICE IMPROVEMENT ON 7TH AND 8TH FLOORS. NEW NON LOAD-BEARING PARTITIONS, CEILINGS, FINISHES, AND INTERIOR DOORS, ELVATOR LOBBIES AND EGRESS STAIR ENCLOSURE.. (NO CHANGE OF USE) PLUMBING, ELECTRICAL, AND HVAC UNDER SEPERATE PERMIT.
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/25/2020
- Certificate of Occupancy
- CofO Corrected More Information
Permit Application Status History
| Permit Finaled | 11/25/2020 | RAFAEL ESPINOZA |
| Submitted | 3/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | AUNG SOE |
| Disabled Access Plans Picked Up | 4/28/2021 | APPLICANT |
| Corrections Issued | 5/6/2021 | AUNG SOE |
| Quality Review Completed | 5/10/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| Green Plans Picked Up | 7/1/2021 | APPLICANT |
| Applicant returned to address corrections | 8/25/2021 | AUNG SOE |
| Plan Check Approved | 8/25/2021 | AUNG SOE |
| Issued | 5/13/2022 | APPLICANT |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 5/24/2021 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 5/24/2021 | LAMBERT GIESSINGER |
| Redevelopment Project Area | Cleared | 6/10/2021 | DAVID URITA |
| Miscellaneous | Cleared | 6/21/2021 | RICHARD REASER |
| Fire Marshal Fire Life Safety | Cleared | 6/30/2021 | WILLIAM JOHNS |
| DAS Clearance | Cleared | 7/1/2021 | AUNG SOE |
| Green Code | Cleared | 7/1/2021 | AARON COSTA |
Contact Information
| Architect | Miroglio,, Naomi Okun; Lic. No.: C22990 | 381 ORANGE STREET OAKLAND, CA 94610 |
| Contractor | Baypost Builders Inc; Lic. No.: 979440-B | 24627 WELBY WAY WEST HILLS, CA 91307 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 11/7/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 11/16/2022 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 12/15/2022 | Partial Approval | KATY RAMIREZ |
| Special/Order Compliance | 4/20/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 11/15/2023 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Green Building Final | 11/15/2023 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 11/15/2023 | Approved | RAFAEL ESPINOZA |
| Special/Order Compliance | 11/21/2023 | Approved | RAFAEL ESPINOZA |