13181 W BRANFORD ST 91331

Certificate Information: 13181 W BRANFORD ST 91331

Application / Permit
21016-10000-05484
Plan Check / Job No.
B21LA03834
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISITING DETACHED ACC. BUIILDING TO ADU PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 10/2/2021
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/5/2021 RACHEL BEYENE
Corrections Issued 5/5/2021 RACHEL BEYENE
Applicant returned to address corrections 8/3/2021 RICARDO RAMIREZ
Plan Check Approved 8/24/2021 RICARDO RAMIREZ
Issued 10/2/2021 APPLICANT
Building Plans Picked Up 10/6/2021 APPLICANT
CofO in Progress 11/6/2023 JENNIFER RABUCHIN
Permit Finaled 1/10/2024 RUBEN SALAS
CofO Issued 1/10/2024 RUBEN SALAS
Permit Finaled 1/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/13/2021 CARLOS AGUILERA
Sewer availability Cleared 5/13/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/11/2021 CARLOS AGUILERA

Contact Information

No Data Available.

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 1/26/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/31/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/31/2022 Approved MICHEL ABAJAN
HVAC-Rough 1/31/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 1/31/2022 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 2/1/2022 No Access for Inspection MICHEL ABAJAN
Insulation 2/2/2022 Approved MICHEL ABAJAN
Drywall Nailing 2/7/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/7/2022 Approved MICHEL ABAJAN
Sewer 2/14/2022 Approved MICHEL ABAJAN
Underground Mechanical 2/14/2022 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 3/10/2022 No Access for Inspection MICHEL ABAJAN
Final 3/10/2022 No Access for Inspection MICHEL ABAJAN
HVAC-Final 3/10/2022 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 3/10/2022 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 3/10/2022 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 4/4/2022 Not Ready for Inspection MICHEL ABAJAN
Final 4/4/2022 Corrections Issued MICHEL ABAJAN
HVAC-Final 4/4/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 4/4/2022 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 4/4/2022 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 8/3/2023 Corrections Issued MICHEL ABAJAN
Final 8/3/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 8/3/2023 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 8/3/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 8/3/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 8/3/2023 Approved MICHEL ABAJAN
Final 8/15/2023 Corrections Issued DAVID MATSON
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Approved DAVID MATSON
Final 8/23/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 11/6/2023 Approved JENNIFER RABUCHIN
Final 11/6/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/6/2023 Approved JENNIFER RABUCHIN
HVAC-Final 11/6/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/6/2023 Approved JENNIFER RABUCHIN