4063 S SUTRO AVE 90008
Certificate Information: 4063 S SUTRO AVE 90008
- Application / Permit
- 21016-10000-05464
- Plan Check / Job No.
- B21LA03816
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (1) SPECIAL CANTILEVERED COLUMN W/ GRADE BEAM.
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofC Issued on 10/27/2021
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | HANS SANTIAGO |
| Corrections Issued | 3/24/2021 | HANS SANTIAGO |
| Quality Review Completed | 3/25/2021 | SAI KHUM |
| Applicant returned to address corrections | 4/12/2021 | HANS SANTIAGO |
| Plan Check Approved | 6/2/2021 | ANDREW SANTIAGO |
| Issued | 7/15/2021 | APPLICANT |
| OK for CofC | 10/27/2021 | DARRYL ARNOLD |
| CofC Issued | 10/27/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/28/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2021 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 8/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 8/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 8/24/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 8/30/2021 | Approved | MARK FERRARI |
| Final | 9/8/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/8/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/8/2021 | Approved | MARK FERRARI |
| Final | 10/7/2021 | Corrections Issued | MARK FERRARI |
| Final | 10/27/2021 | Not Ready for Inspection | DARRYL ARNOLD |