635 W 23RD ST 90007
Certificate Information: 635 W 23RD ST 90007
- Application / Permit
- 21016-10000-05463
- Plan Check / Job No.
- B21LA03815
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install (4) SCCs
- Permit Issued
- Issued on 11/22/2022
- Issuing Office
- Current Status
- Issued on 11/22/2022
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | JESSE VIDUYA |
| Corrections Issued | 3/25/2021 | JESSE VIDUYA |
| Quality Review Completed | 4/5/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 5/17/2021 | JESSE VIDUYA |
| Plan Check Approved | 7/23/2021 | JESSE VIDUYA |
| Issued | 11/22/2022 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 4/27/2021 | KATIE DEBIASE |
| ZI | Cleared | 5/11/2021 | MAXFIELD VERMY |
| Tenant Habitability Plan | Cleared | 11/17/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Martinez Building And Development; Lic. No.: 1031582-B | 10113 HARVEST AVE SANTA FE SPRINGS, CA 90670 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2025 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/1/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/6/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/7/2025 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 10/7/2025 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 10/7/2025 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 10/8/2025 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/1/2026 | Partial Approval | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Not Ready | RONALD JIMENEZ |
| Final | 4/9/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 4/9/2026 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/9/2026 | Corrections Issued | DARRYL ARNOLD |