3774 N CAZADOR ST 90065
Certificate Information: 3774 N CAZADOR ST 90065
- Application / Permit
- 21016-10000-05373
- Plan Check / Job No.
- B20LA24418
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2021 | KEVIN MORALES |
| Corrections Issued | 3/3/2021 | KEVIN MORALES |
| Plan Check Approved | 4/26/2021 | KEVIN MORALES |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 1/26/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/2/2022 | DEROLD HAUFF |
| Permit Finaled | 2/2/2022 | DEROLD HAUFF |
| CofO Issued | 2/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/6/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | JEANIE LAM |
| Specific Plan | Cleared | 4/7/2021 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 4/20/2021 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/7/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/7/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/17/2021 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 6/17/2021 | Partial Approval | BRAD BESCOS |
| BUILDING-Rough-Frame | 7/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 7/13/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/16/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/16/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/2/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/2/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/19/2021 | No Access for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 8/25/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 10/19/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/25/2021 | Approved | ADAM ESCOTO |
| Gas Test | 10/25/2021 | Approved | ADAM ESCOTO |
| Shower Pan | 11/22/2021 | Approved | MASHEL JONGERT |
| Final | 1/13/2022 | Corrections Issued | OSVALDO PARAMO |
| Reinforced Masonry Frame | 1/13/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 1/13/2022 | Approved | OSVALDO PARAMO |
| Final | 1/25/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |