3774 N CAZADOR ST 90065

Certificate Information: 3774 N CAZADOR ST 90065

Application / Permit
21016-10000-05373
Plan Check / Job No.
B20LA24418
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 2/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/3/2021 KEVIN MORALES
Corrections Issued 3/3/2021 KEVIN MORALES
Plan Check Approved 4/26/2021 KEVIN MORALES
Issued 4/30/2021 APPLICANT
CofO in Progress 1/26/2022 HAMIK HARTOUNIAN
Permit Finaled 2/2/2022 DEROLD HAUFF
Permit Finaled 2/2/2022 DEROLD HAUFF
CofO Issued 2/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/6/2021 JEANIE LAM
Sewer availability Cleared 4/6/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/7/2021 JEANIE LAM
Specific Plan Cleared 4/7/2021 NASHYA JENSEN
Grading Pre-Inspection Cleared 4/20/2021 BARTON HOLMES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/7/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/7/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 6/15/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/17/2021 Approved HAMIK HARTOUNIAN
Special/Order Compliance 6/17/2021 Partial Approval BRAD BESCOS
BUILDING-Rough-Frame 7/13/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 7/13/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 7/13/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 7/13/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 7/16/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/16/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/16/2021 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/2/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/2/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/19/2021 No Access for Inspection BRIAN SULLIVAN
HVAC-Rough 8/25/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/19/2021 Approved HAMIK HARTOUNIAN
Insulation 10/19/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/25/2021 Approved ADAM ESCOTO
Gas Test 10/25/2021 Approved ADAM ESCOTO
Shower Pan 11/22/2021 Approved MASHEL JONGERT
Final 1/13/2022 Corrections Issued OSVALDO PARAMO
Reinforced Masonry Frame 1/13/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 1/13/2022 Approved OSVALDO PARAMO
Final 1/25/2022 OK to Issue CofO HAMIK HARTOUNIAN