3357 N WONDER VIEW DR 90068
Certificate Information: 3357 N WONDER VIEW DR 90068
- Application / Permit
- 21016-10000-05341
- Plan Check / Job No.
- B21LA03716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePLAN CHECK* INTERIOR & EXTERIOR REMODEL & NEW 51'-5" X 9'-6" BALCONY ADDITION TO (E) SINGLE FAMILY DWELLING W/ATT GARAGE
- Permit Issued
- Issued on 8/26/2021
- Issuing Office
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | LAMAR DAVIS |
| Corrections Issued | 3/16/2021 | LAMAR DAVIS |
| Quality Review Completed | 3/24/2021 | LARRY LEE |
| Applicant returned to address corrections | 6/1/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 7/2/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 7/23/2021 | LAMAR DAVIS |
| Plan Check Approved | 8/20/2021 | LAMAR DAVIS |
| Issued | 8/26/2021 | APPLICANT |
| CofO in Progress | 11/17/2023 | BRIAN SULLIVAN |
| CofO Issued | 12/29/2023 | DEROLD HAUFF |
| Permit Finaled | 12/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/30/2021 | OLGA AYALA |
| Grading Pre-Inspection | Cleared | 6/24/2021 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 6/24/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 8/4/2021 | KURT CORRAL |
Contact Information
| Contractor | Providence Construction Group; Lic. No.: 950289-B | 16701 ALEXANDER AVENUE CERRITOS, CA 90703 |
| Engineer | Remon,, Jose Ernesto; Lic. No.: C32421 | 6571 KILDA CIRCLE HUNTINGTON BEACH, CA 92647 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 12/7/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/6/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/21/2022 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/21/2022 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 8/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/2/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/16/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 8/16/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/16/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/6/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 9/6/2022 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/6/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 10/3/2022 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/3/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/19/2022 | Approved | BRIAN SULLIVAN |
| Insulation | 10/19/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/19/2022 | Partial Approval | BRIAN SULLIVAN |
| Drywall Nailing | 11/14/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 11/14/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Shower Pan | 11/16/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/23/2022 | Approved | BRIAN SULLIVAN |
| Light Gage Steel Frame | 2/8/2023 | Conditional Approval | BRIAN SULLIVAN |
| HVAC-Rough | 6/8/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 9/5/2023 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 9/5/2023 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 9/5/2023 | Corrections Issued | BRIAN SULLIVAN |
| Final | 9/14/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 9/14/2023 | Approved | BRIAN SULLIVAN |
| Final | 10/17/2023 | Partial Inspection | BRIAN SULLIVAN |
| Final | 11/13/2023 | OK to Issue CofO | BRIAN SULLIVAN |