2657 S REDONDO BLVD 90016
Certificate Information: 2657 S REDONDO BLVD 90016
- Application / Permit
- 21016-10000-05324
- Plan Check / Job No.
- B21LA03676
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT AS PER LABC CH. 93. INSTALL (2) SCCS.
- Permit Issued
- Issued on 6/28/2021
- Issuing Office
- Current Status
- CofC Issued on 11/8/2021
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | VARAND SARKISIAN |
| Corrections Issued | 3/16/2021 | VARAND SARKISIAN |
| Quality Review Completed | 3/18/2021 | HANS SANTIAGO |
| Building Plans Picked Up | 3/23/2021 | APPLICANT |
| Applicant returned to address corrections | 4/14/2021 | VARAND SARKISIAN |
| Plan Check Approved | 5/5/2021 | VARAND SARKISIAN |
| Issued | 6/28/2021 | APPLICANT |
| OK for CofC | 10/14/2021 | MARK FERRARI |
| CofC Issued | 11/8/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/24/2021 | MICHAEL SOTO |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Ark Construction Co; Lic. No.: 471822-B | 6131 SAN VICENTE BLVD LOS ANGELES, CA 90048 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2021 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/8/2021 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 9/8/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 9/8/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 9/15/2021 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 9/15/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/15/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 9/15/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 9/16/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/23/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 10/14/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 10/14/2021 | Approved | MARK FERRARI |