180 1/2-182 W 42ND ST 90037

Certificate Information: 180 1/2-182 W 42ND ST 90037

Application / Permit
21016-10000-05317
Plan Check / Job No.
B21LA03670
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 2-CAR GARAGE ON 1ST FLOOR OF (E) REAR UNIT INTO A PROPOSED ADU OF 399 SQFT PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 4/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 SERGIO GUTIERREZ
Corrections Issued 3/6/2021 SERGIO GUTIERREZ
Applicant returned to address corrections 7/6/2021 SINA KHOSRAVI
Applicant returned to address corrections 8/26/2021 TSE MING HUANG
Applicant returned to address corrections 10/28/2021 TSE MING HUANG
Applicant returned to address corrections 1/13/2022 ADAM HEGAZI
Plan Check Approved 1/24/2022 ADAM HEGAZI
Building Plans Picked Up 2/9/2022 APPLICANT
Issued 3/2/2022 APPLICANT
CofO in Progress 4/13/2023 BRENDAN MORELLI
Permit Finaled 4/15/2023 DEROLD HAUFF
CofO Issued 4/15/2023 DEROLD HAUFF
Permit Finaled 4/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/8/2021 JEANIE LAM
Sewer availability Cleared 4/8/2021 JEANIE LAM
Tenant Habitability Plan Cleared 4/13/2021 ISMAEL HERNANDEZ
Hydrant and Access approval Cleared 5/19/2021 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/17/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 6/17/2022 Corrections Issued HORACE FULTZ
Green Building Rough 6/17/2022 Approved HORACE FULTZ
METHANE-Rough 6/17/2022 Approved HORACE FULTZ
PLUMBING-Rough 6/17/2022 Approved HORACE FULTZ
ELECTRICAL-Rough 7/28/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 7/28/2022 Approved JOAQUIN GREENOUGH
Wood Frame 7/28/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/8/2022 Approved ENRIQUE MIRELES
Insulation 8/8/2022 Approved ENRIQUE MIRELES
Drywall Nailing 8/15/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/15/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/15/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Final 9/15/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Final 9/15/2022 Not Ready for Inspection SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Not Ready SHAVONNE ESPINOZA
Smoke Detectors 9/15/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 9/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Final 9/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Final 9/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Not Ready SHAVONNE ESPINOZA
BUILDING-Rough-Frame 10/6/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 10/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/21/2022 Approved ALIZAH MAYAGOITIA
Final 10/21/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 10/21/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 10/21/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 10/21/2022 Approved ALIZAH MAYAGOITIA
Final 4/12/2023 OK to Issue CofO BRENDAN MORELLI
Service/Power Release 4/12/2023 Approved BRENDAN MORELLI