3765 S GLOBE AVE 90066

Certificate Information: 3765 S GLOBE AVE 90066

Application / Permit
21016-10000-05311
Plan Check / Job No.
B21LA03660
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL 1340SF (E) SFD 1 OF 2
Permit Issued
Issued on 9/13/2022
Issuing Office
Metro
Current Status
Permit Finaled on 3/23/2026

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 JESSE VIDUYA
Corrections Issued 5/24/2021 JESSE VIDUYA
Quality Review Completed 5/26/2021 ALLEN MANALANSAN
Building Plans Picked Up 6/2/2021 APPLICANT
Applicant returned to address corrections 10/21/2021 JESSE VIDUYA
Applicant returned to address corrections 1/6/2022 JESSE VIDUYA
Applicant returned to address corrections 7/8/2022 JESSE VIDUYA
Applicant returned to address corrections 8/15/2022 JESSE VIDUYA
Plan Check Approved 9/8/2022 JESSE VIDUYA
Issued 9/13/2022 APPLICANT
Permit Finaled 3/19/2026 RYAN BARNES

Permit Application Clearance Information

ZI Cleared 5/12/2022 MAXFIELD VERMY
ZI Cleared 5/12/2022 MAXFIELD VERMY
Specific Plan Cleared 5/16/2022 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Chiang,, Tzuu Pien; Lic. No.: C72618 18295 AGUIRO STREET      ROWLAND HEIGHTS, CA 91748

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/14/2022 No Access for Inspection MARIAN PODPORA
Pre-Inspection 10/17/2022 No Access for Inspection MARIAN PODPORA
Footing/Foundation/Slab 10/31/2022 Corrections Issued RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Not Ready for Inspection RYAN BARNES
Footing/Foundation/Slab 11/7/2022 Not Ready for Inspection RYAN BARNES
Drywall Nailing 11/14/2022 Not Ready for Inspection MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Corrections Issued MARIAN PODPORA
Green Building Rough 11/14/2022 Not Ready for Inspection MARIAN PODPORA
Footing/Foundation/Slab 12/16/2022 Not Ready for Inspection MARIAN PODPORA
Footing/Foundation/Slab 12/28/2022 Corrections Issued MARIAN PODPORA
Footing/Foundation/Slab 4/3/2023 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 7/13/2023 Corrections Issued ANDREW BEELI
Excavation/Setback/Form/Re-Bar 6/14/2024 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 6/17/2024 Approved RYAN BARNES
BUILDING-Rough-Frame 7/15/2024 Partial Inspection RYAN BARNES
Green Building Rough 7/15/2024 Approved RYAN BARNES
MERV13>=Rough 7/15/2024 Not Ready for Inspection RYAN BARNES
Service/Power Release 11/20/2025 Not Ready for Inspection RYAN BARNES
Service/Power Release 12/2/2025 Approved RYAN BARNES
BUILDING-Rough-Frame 12/16/2025 Approved RYAN BARNES
Drywall Nailing 12/16/2025 Approved RYAN BARNES
ELECTRICAL-Final 12/16/2025 Corrections Issued RYAN BARNES
Final 12/16/2025 Not Ready for Inspection RYAN BARNES
Green Building Final 12/16/2025 Approved RYAN BARNES
HVAC-Final 12/16/2025 Approved RYAN BARNES
MERV13>=Final 12/16/2025 Approved RYAN BARNES
MERV13>=Rough 12/16/2025 Approved RYAN BARNES
PLUMBING-Final 12/16/2025 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Not Ready RYAN BARNES
Smoke Detectors 12/16/2025 Approved RYAN BARNES
ELECTRICAL-Final 3/19/2026 Approved RYAN BARNES
Final 3/19/2026 Permit Finaled RYAN BARNES
HVAC-Final 3/19/2026 Approved RYAN BARNES
PLUMBING-Final 3/19/2026 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Approved RYAN BARNES