3765 S GLOBE AVE 90066
Certificate Information: 3765 S GLOBE AVE 90066
- Application / Permit
- 21016-10000-05311
- Plan Check / Job No.
- B21LA03660
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL 1340SF (E) SFD 1 OF 2
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/23/2026
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | JESSE VIDUYA |
| Corrections Issued | 5/24/2021 | JESSE VIDUYA |
| Quality Review Completed | 5/26/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
| Applicant returned to address corrections | 10/21/2021 | JESSE VIDUYA |
| Applicant returned to address corrections | 1/6/2022 | JESSE VIDUYA |
| Applicant returned to address corrections | 7/8/2022 | JESSE VIDUYA |
| Applicant returned to address corrections | 8/15/2022 | JESSE VIDUYA |
| Plan Check Approved | 9/8/2022 | JESSE VIDUYA |
| Issued | 9/13/2022 | APPLICANT |
| Permit Finaled | 3/19/2026 | RYAN BARNES |
Permit Application Clearance Information
| ZI | Cleared | 5/12/2022 | MAXFIELD VERMY |
| ZI | Cleared | 5/12/2022 | MAXFIELD VERMY |
| Specific Plan | Cleared | 5/16/2022 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiang,, Tzuu Pien; Lic. No.: C72618 | 18295 AGUIRO STREET ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/14/2022 | No Access for Inspection | MARIAN PODPORA |
| Pre-Inspection | 10/17/2022 | No Access for Inspection | MARIAN PODPORA |
| Footing/Foundation/Slab | 10/31/2022 | Corrections Issued | RYAN BARNES |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Not Ready for Inspection | RYAN BARNES |
| Footing/Foundation/Slab | 11/7/2022 | Not Ready for Inspection | RYAN BARNES |
| Drywall Nailing | 11/14/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Corrections Issued | MARIAN PODPORA |
| Green Building Rough | 11/14/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Footing/Foundation/Slab | 12/16/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Footing/Foundation/Slab | 12/28/2022 | Corrections Issued | MARIAN PODPORA |
| Footing/Foundation/Slab | 4/3/2023 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 7/13/2023 | Corrections Issued | ANDREW BEELI |
| Excavation/Setback/Form/Re-Bar | 6/14/2024 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 6/17/2024 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 7/15/2024 | Partial Inspection | RYAN BARNES |
| Green Building Rough | 7/15/2024 | Approved | RYAN BARNES |
| MERV13>=Rough | 7/15/2024 | Not Ready for Inspection | RYAN BARNES |
| Service/Power Release | 11/20/2025 | Not Ready for Inspection | RYAN BARNES |
| Service/Power Release | 12/2/2025 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 12/16/2025 | Approved | RYAN BARNES |
| Drywall Nailing | 12/16/2025 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 12/16/2025 | Corrections Issued | RYAN BARNES |
| Final | 12/16/2025 | Not Ready for Inspection | RYAN BARNES |
| Green Building Final | 12/16/2025 | Approved | RYAN BARNES |
| HVAC-Final | 12/16/2025 | Approved | RYAN BARNES |
| MERV13>=Final | 12/16/2025 | Approved | RYAN BARNES |
| MERV13>=Rough | 12/16/2025 | Approved | RYAN BARNES |
| PLUMBING-Final | 12/16/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Not Ready | RYAN BARNES |
| Smoke Detectors | 12/16/2025 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 3/19/2026 | Approved | RYAN BARNES |
| Final | 3/19/2026 | Permit Finaled | RYAN BARNES |
| HVAC-Final | 3/19/2026 | Approved | RYAN BARNES |
| PLUMBING-Final | 3/19/2026 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | RYAN BARNES |