14760 W SEPTO ST 91345

Certificate Information: 14760 W SEPTO ST 91345

Application / Permit
21016-10000-05232
Plan Check / Job No.
B21LA03596
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Conversion of an (E) detached 2-car garage into an ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 3/24/2021
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/3/2021 HELEN NGUYEN
Corrections Issued 3/4/2021 HELEN NGUYEN
Applicant returned to address corrections 3/15/2021 HELEN NGUYEN
Plan Check Approved 3/17/2021 HELEN NGUYEN
Issued 3/24/2021 APPLICANT
CofO in Progress 10/27/2023 JENNIFER RABUCHIN
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/8/2021 GABRIEL ROBLES
Sewer availability Cleared 3/8/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/10/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/23/2021 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/3/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/11/2021 Partial Approval JENNIFER RABUCHIN
Sewer 5/11/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 5/11/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
Final 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Final 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/21/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 6/21/2021 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/17/2021 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 9/22/2021 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/25/2022 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 5/31/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/31/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 8/10/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/15/2022 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Approved JENNIFER RABUCHIN
Green Building Rough 9/15/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 9/15/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 9/15/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/24/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/24/2023 Approved JENNIFER RABUCHIN
Green Building Rough 3/24/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 3/24/2023 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 3/24/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Final 3/24/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 4/24/2023 Approved MATTHEW NELSON
Drywall Nailing 5/5/2023 Approved JENNIFER RABUCHIN
Final 8/17/2023 No Access for Inspection JUAN VALENZUELA
Green Building Final 8/17/2023 No Access for Inspection JUAN VALENZUELA
Smoke Detectors 8/17/2023 No Access for Inspection JUAN VALENZUELA
ELECTRICAL-Final 9/19/2023 Corrections Issued JENNIFER RABUCHIN
Final 9/19/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/19/2023 Approved JENNIFER RABUCHIN
HVAC-Final 9/19/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 9/19/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 9/19/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/26/2023 Approved JENNIFER RABUCHIN
Final 10/26/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 10/26/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/26/2023 Approved JENNIFER RABUCHIN