538 N PALISADES DR 90272
Certificate Information: 538 N PALISADES DR 90272
- Application / Permit
- 21016-10000-05214
- Plan Check / Job No.
- B21LA03571
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Renovation of (E) Restaurant and Bar.
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/15/2021
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/18/2021 | SALVADOR QUINTANILLA |
| Quality Review Completed | 3/18/2021 | PETER KIM |
| Building Plans Picked Up | 3/24/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 4/12/2021 | APPLICANT |
| Green Plans Picked Up | 6/10/2021 | APPLICANT |
| Applicant returned to address corrections | 6/11/2021 | SALVADOR QUINTANILLA |
| Plan Check Approved | 8/3/2021 | SALVADOR QUINTANILLA |
| Issued | 8/6/2021 | APPLICANT |
| Permit Finaled | 12/14/2021 | GRANT WOODS |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/13/2021 | DANIEL CORONADO |
| ZA Case | Cleared | 4/19/2021 | DANIEL CORONADO |
| Sewer availability | Cleared | 4/20/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | ANTHONY MAINEZ |
| Green Code | Cleared | 5/11/2021 | SALVADOR QUINTANILLA |
| DAS Clearance | Cleared | 5/20/2021 | SALVADOR QUINTANILLA |
| Food Service Establishment | Cleared | 7/8/2021 | PAWAN VERMA |
| Food establishment approval | Cleared | 7/8/2021 | LACDHS APPROVED |
Contact Information
| Contractor | Engine Construction Inc; Lic. No.: 1024143-B | 13365 W WASHINGTON BVLD APT 305 LOS ANGELES, CA 90066 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/11/2021 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 8/11/2021 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 8/11/2021 | Not Ready for Inspection | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 8/13/2021 | Approved | GRANT WOODS |
| Light Gage Steel Frame | 8/13/2021 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 8/18/2021 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 8/24/2021 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 8/30/2021 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 9/2/2021 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 9/10/2021 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 9/28/2021 | No Access for Inspection | GRANT WOODS |
| T-Bar Ceiling | 10/6/2021 | Approved | GRANT WOODS |
| Final | 12/9/2021 | Partial Inspection | GRANT WOODS |
| Green Building Final | 12/9/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 12/9/2021 | Approved | GRANT WOODS |
| Final | 12/14/2021 | Permit Finaled | GRANT WOODS |