11928 S BEATRICE ST 90230
Certificate Information: 11928 S BEATRICE ST 90230
- Application / Permit
- 21016-10000-05206
- Plan Check / Job No.
- B21LA03561
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) GARAGE CONVERTED TO 1-BED ROOM UNIT ADU (370SQFT) PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | RACHEL BEYENE |
| Corrections Issued | 3/5/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 8/26/2021 | RAMA DABADGE |
| Plan Check Approved | 11/18/2021 | JOSEPH RAFOLS |
| Building Plans Picked Up | 11/19/2021 | APPLICANT |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 2/19/2025 | DAVID FEILER |
| Permit Finaled | 2/19/2025 | RICHARD STEINBACH |
| CofO Issued | 2/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/26/2021 | RIDWAN HARDY |
| Address approval | Cleared | 7/12/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/12/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Rati Construction Inc; Lic. No.: 1073152-B | 15046 E NELSON AVE #6 CITY OF INDUSTRY, CA 91744 |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/25/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/25/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 1/25/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/1/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/1/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 3/1/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/8/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 3/8/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 3/8/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 4/4/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 4/4/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 4/4/2023 | Approved | HERBERT GIRON |
| Underground Mechanical | 4/4/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/28/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 4/28/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 4/28/2023 | Approved | HERBERT GIRON |
| Insulation | 9/11/2023 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 11/14/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Insulation | 3/1/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 7/19/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 7/19/2024 | Corrections Issued | BOBBY KEY |
| Shower Pan | 7/19/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/16/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 8/16/2024 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/22/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 9/26/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Rough | 9/26/2024 | Approved | TEMISTOCLES CAAL |
| MERV13>=Rough | 9/26/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/10/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 10/10/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/31/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 12/31/2024 | Corrections Issued | TEMISTOCLES CAAL |
| MERV13>=Final | 12/31/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/31/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 12/31/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/11/2025 | Approved | MICHAEL ALLEN |
| Final | 2/11/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 2/11/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 2/11/2025 | Approved | MICHAEL ALLEN |
| Final | 2/19/2025 | OK to Issue CofO | DAVID FEILER |