221 S WINDSOR BLVD 90004

Certificate Information: 221 S WINDSOR BLVD 90004

Application / Permit
21016-10000-05161
Plan Check / Job No.
B21LA03514
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: Convert existing 28'-2.5" X 20'-1.5" detached garage to ADU of same size. New trellis and deck attached to ADU.
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 ARSALAN SHABESTARI
Corrections Issued 3/28/2021 ARSALAN SHABESTARI
Quality Review Completed 4/12/2021 MICHAEL PEREZ
Plan Check Approved 6/27/2021 ARSALAN SHABESTARI
Issued 10/20/2021 APPLICANT
CofO in Progress 12/7/2022 JEFFREY MEAD
Permit Finaled 12/10/2022 DEROLD HAUFF
CofO Issued 12/10/2022 DEROLD HAUFF
Permit Finaled 12/10/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/30/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 4/30/2021 CELINA MORENO
Sewer availability Cleared 4/30/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/3/2021 CELINA MORENO
CPC Cleared 6/11/2021 LYDIA CHAPMAN
CPC Cleared 6/11/2021 LYDIA CHAPMAN
CPC Cleared 6/11/2021 LYDIA CHAPMAN
Construction near power lines Cleared 6/11/2021 WALTER RAMIREZ
Construction within easement Cleared 6/11/2021 WALTER RAMIREZ
HPOZ Cleared 6/11/2021 LYDIA CHAPMAN

Contact Information

Architect Kim,, Peter Sung Taek; Lic. No.: NA29012       ,
Contractor Haneul Yoo Inc; Lic. No.: 986509-B 3311 W 3RD ST #1-253      LOS ANGELES, CA 90020
Engineer Kwon,, Ohsung; Lic. No.: NA85429       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/9/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 1/14/2022 Conditional Approval JOSEPH MCGARRY
METHANE-Barrier 1/14/2022 Approved JOSEPH MCGARRY
METHANE-Subgrade 1/14/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 3/10/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 3/10/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Rough 4/22/2022 Approved ADAM ESCOTO
HVAC-Rough 4/22/2022 Approved ADAM ESCOTO
PLUMBING-Rough 4/22/2022 Not Ready for Inspection ADAM ESCOTO
BUILDING-Rough-Frame 4/28/2022 Corrections Issued SHAVONNE ESPINOZA
Green Building Rough 4/28/2022 Not Ready for Inspection SHAVONNE ESPINOZA
METHANE-Rough 4/28/2022 Corrections Issued SHAVONNE ESPINOZA
PLUMBING-Rough 4/28/2022 Approved SHAVONNE ESPINOZA
Deputy Wood Construction 5/5/2022 Conditional Approval ADAM ESCOTO
METHANE-Final 5/5/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 5/9/2022 Approved SHAVONNE ESPINOZA
Wood Frame 5/9/2022 Approved SHAVONNE ESPINOZA
BUILDING-Rough-Frame 5/12/2022 Conditional Approval SHAVONNE ESPINOZA
Green Building Rough 5/12/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Green Building Rough 5/18/2022 Partial Approval SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/24/2022 Corrections Issued SHAVONNE ESPINOZA
Insulation 6/1/2022 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 6/1/2022 Partial Approval SHAVONNE ESPINOZA
Insulation 6/22/2022 Approved JEFFREY MEAD
Drywall Nailing 6/29/2022 Approved JEFFREY MEAD
Drywall Nailing 7/11/2022 Approved JEFFREY MEAD
Shower Pan 7/11/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 10/18/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 10/18/2022 Corrections Issued JEFFREY MEAD
Final 10/18/2022 Not Ready for Inspection JEFFREY MEAD
Footing/Foundation/Slab 10/18/2022 Approved JEFFREY MEAD
Green Building Final 10/18/2022 Approved JEFFREY MEAD
Green Building Rough 10/18/2022 Approved JEFFREY MEAD
HVAC-Final 10/18/2022 Corrections Issued JEFFREY MEAD
PLUMBING-Final 10/18/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 10/18/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 10/27/2022 Approved JEFFREY MEAD
Final 10/27/2022 Corrections Issued JEFFREY MEAD
HVAC-Final 10/27/2022 Approved JEFFREY MEAD
PLUMBING-Final 10/27/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved JEFFREY MEAD
Final 11/1/2022 Corrections Issued JEFFREY MEAD
Final 11/18/2022 Corrections Issued JOSEPH MCGARRY
Final 11/30/2022 Partial Inspection JEFFREY MEAD
Final 12/7/2022 OK to Issue CofO JEFFREY MEAD