1322 1/2-1/4 S 2ND AVE 90019
Certificate Information: 1322 1/2-1/4 S 2ND AVE 90019
- Application / Permit
- 21016-10000-05158
- Plan Check / Job No.
- B21LA03510
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Conversion of an (E) 4-parking spaces at an (E) apartment building into (2) ADUs. Attached ADUs per state law GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 7/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | HELEN NGUYEN |
| Corrections Issued | 3/11/2021 | HELEN NGUYEN |
| Quality Review Completed | 3/24/2021 | MINYE PAK |
| Applicant returned to address corrections | 8/27/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/27/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/14/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/22/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/28/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/5/2022 | HELEN NGUYEN |
| Plan Check Approved | 4/23/2022 | HELEN NGUYEN |
| Issued | 4/26/2022 | APPLICANT |
| Green Plans Picked Up | 9/12/2023 | APPLICANT |
| CofO in Progress | 7/3/2024 | JACOB MYERS |
| Permit Finaled | 7/3/2024 | WINSTON DUNNING |
| CofO Issued | 7/3/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/8/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 4/9/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 6/2/2021 | RIDWAN HARDY |
| Miscellaneous | Cleared | 7/22/2021 | HELEN NGUYEN |
| Green Code | Cleared | 7/23/2021 | HELEN NGUYEN |
| Community Plan Implem. Overlay | Cleared | 8/31/2021 | KYLE WINSTON |
Contact Information
| Contractor | Cedar Construction & Development Inc; Lic. No.: 554550-B | 10234 NATIONAL BLVD #1 LOS ANGELES, CA 90034 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
| Engineer | Salehipour,, Sassan Abolghasem; Lic. No.: C44172 | 1290 NORTH LAKE AVENUE STE 204 PASADENA, CA 91104 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/18/2022 | Conditional Approval | WINSTON DUNNING |
| Footing/Foundation/Slab | 7/18/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 8/1/2022 | Approved | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Partial Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 10/24/2022 | Partial Inspection | KATY RAMIREZ |
| Insulation | 11/23/2022 | Approved | GREGORY POMISH |
| Deputy Wood Construction | 12/1/2022 | Conditional Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 12/8/2022 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 12/16/2022 | Partial Approval | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 12/20/2022 | Approved | ALFREDO LOPEZ |
| Final | 4/5/2024 | Partial Inspection | JACOB MYERS |
| Green Building Final | 4/5/2024 | Approved | JACOB MYERS |
| Green Building Rough | 4/5/2024 | Approved | JACOB MYERS |
| METHANE-Final | 4/5/2024 | Approved | JACOB MYERS |
| METHANE-Rough | 4/5/2024 | Approved | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 4/5/2024 | Approved | JACOB MYERS |
| Wood Frame | 4/5/2024 | Approved | JACOB MYERS |
| Final | 7/3/2024 | OK to Issue CofO | JACOB MYERS |