7945 N FALLBROOK AVE 91304

Certificate Information: 7945 N FALLBROOK AVE 91304

Application / Permit
21016-10000-05145
Plan Check / Job No.
B21LA03500
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) 400 SF garage to ADU per GCS 68582.2 (e)(1)(A). All work per WFPP.
Permit Issued
Issued on 10/2/2021
Issuing Office
Current Status
CofO Issued on 10/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2021 APPLICANT
Assigned to Plan Check Engineer 4/1/2021 AARON COSTA
Corrections Issued 4/1/2021 AARON COSTA
Applicant returned to address corrections 8/9/2021 LUKE GONZALES
Plan Check Approved 9/9/2021 RAHEL BEYENE
Building Plans Picked Up 9/10/2021 APPLICANT
Issued 10/2/2021 APPLICANT
CofO in Progress 10/25/2022 CHRIS CHRISTENSEN
Permit Finaled 10/31/2022 JOHN JANSON
CofO Issued 10/31/2022 JOHN JANSON
Permit Finaled 10/31/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/29/2021 ADRIAN CASTRO
Sewer availability Cleared 4/29/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/13/2021 ADRIAN CASTRO

Contact Information

No Data Available.

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/9/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 11/9/2021 Corrections Issued DAVID STEPANYAN
Special/Order Compliance 11/9/2021 Corrections Issued DAVID STEPANYAN
Underground Mechanical 11/9/2021 Not Ready for Inspection DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 11/15/2021 Approved DAVID STEPANYAN
Footing/Foundation/Slab 11/15/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 11/15/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 12/7/2021 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 12/7/2021 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 12/7/2021 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 12/23/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 12/23/2021 Corrections Issued DAVID STEPANYAN
Green Building Rough 12/23/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 12/23/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 12/23/2021 Corrections Issued DAVID STEPANYAN
Sewer 12/23/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 1/24/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 1/24/2022 Not Ready for Inspection PETER FOLLING
Green Building Rough 1/24/2022 Not Ready for Inspection PETER FOLLING
HVAC-Rough 1/24/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 1/24/2022 Corrections Issued PETER FOLLING
Sewer 1/24/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 2/1/2022 Approved PETER FOLLING
Green Building Rough 2/1/2022 Not Ready for Inspection PETER FOLLING
HVAC-Rough 2/1/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 2/1/2022 Approved PETER FOLLING
Sewer 2/1/2022 Approved PETER FOLLING
Shower Pan 2/1/2022 Approved PETER FOLLING
Underground Mechanical 2/1/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 2/14/2022 Approved PETER FOLLING
Green Building Rough 2/14/2022 Approved PETER FOLLING
HVAC-Rough 2/14/2022 Approved PETER FOLLING
Insulation 2/14/2022 Approved PETER FOLLING
Interior/Exterior Lathing 2/14/2022 Partial Approval PETER FOLLING
Drywall Nailing 3/16/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 3/16/2022 Approved JESUS PINEDA
Pre-Inspection 4/19/2022 Approved CHRIS CHRISTENSEN
Final 9/7/2022 Corrections Issued SEAN WIRCH
Green Building Final 9/7/2022 Corrections Issued SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Not Ready SEAN WIRCH
Smoke Detectors 9/7/2022 Not Ready for Inspection SEAN WIRCH
ELECTRICAL-Final 9/16/2022 Approved CHRIS CHRISTENSEN
Final 9/16/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 9/16/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 9/16/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/16/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 9/16/2022 Approved CHRIS CHRISTENSEN
Final 10/24/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 10/24/2022 Approved CHRIS CHRISTENSEN