7945 N FALLBROOK AVE 91304
Certificate Information: 7945 N FALLBROOK AVE 91304
- Application / Permit
- 21016-10000-05145
- Plan Check / Job No.
- B21LA03500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 400 SF garage to ADU per GCS 68582.2 (e)(1)(A). All work per WFPP.
- Permit Issued
- Issued on 10/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2021 | AARON COSTA |
| Corrections Issued | 4/1/2021 | AARON COSTA |
| Applicant returned to address corrections | 8/9/2021 | LUKE GONZALES |
| Plan Check Approved | 9/9/2021 | RAHEL BEYENE |
| Building Plans Picked Up | 9/10/2021 | APPLICANT |
| Issued | 10/2/2021 | APPLICANT |
| CofO in Progress | 10/25/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/31/2022 | JOHN JANSON |
| CofO Issued | 10/31/2022 | JOHN JANSON |
| Permit Finaled | 10/31/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/29/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | ADRIAN CASTRO |
Contact Information
| No Data Available. |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2021 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/9/2021 | Corrections Issued | DAVID STEPANYAN |
| Special/Order Compliance | 11/9/2021 | Corrections Issued | DAVID STEPANYAN |
| Underground Mechanical | 11/9/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/15/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 11/15/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/7/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/7/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 12/7/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/23/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 12/23/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 12/23/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 12/23/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 12/23/2021 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 12/23/2021 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 1/24/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 1/24/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 1/24/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 1/24/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 1/24/2022 | Corrections Issued | PETER FOLLING |
| Sewer | 1/24/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 2/1/2022 | Approved | PETER FOLLING |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 2/1/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 2/1/2022 | Approved | PETER FOLLING |
| Sewer | 2/1/2022 | Approved | PETER FOLLING |
| Shower Pan | 2/1/2022 | Approved | PETER FOLLING |
| Underground Mechanical | 2/1/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 2/14/2022 | Approved | PETER FOLLING |
| Green Building Rough | 2/14/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 2/14/2022 | Approved | PETER FOLLING |
| Insulation | 2/14/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 2/14/2022 | Partial Approval | PETER FOLLING |
| Drywall Nailing | 3/16/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/16/2022 | Approved | JESUS PINEDA |
| Pre-Inspection | 4/19/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 9/7/2022 | Corrections Issued | SEAN WIRCH |
| Green Building Final | 9/7/2022 | Corrections Issued | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Not Ready | SEAN WIRCH |
| Smoke Detectors | 9/7/2022 | Not Ready for Inspection | SEAN WIRCH |
| ELECTRICAL-Final | 9/16/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 9/16/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 9/16/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 9/16/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 9/16/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/16/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 10/24/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 10/24/2022 | Approved | CHRIS CHRISTENSEN |