687 1/2 E 49TH ST 90011
Certificate Information: 687 1/2 E 49TH ST 90011
- Application / Permit
- 21016-10000-05142
- Plan Check / Job No.
- B21LA03496
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of (E) garage/storage into one story detached ADU per LAMC 12.22 A33 (c) and (d)
- Permit Issued
- Issued on 9/21/2021
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | RAMA DABADGE |
| Corrections Issued | 4/14/2021 | RAMA DABADGE |
| Applicant returned to address corrections | 6/10/2021 | SHANGQIN XIE |
| Plan Check Approved | 8/9/2021 | SAMUEL GONZALEZ |
| Issued | 9/21/2021 | APPLICANT |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| CofO in Progress | 3/5/2024 | ALEJANDRO DE ARTOLA |
| CofO Issued | 3/18/2024 | DEROLD HAUFF |
| Permit Finaled | 3/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 4/23/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 4/28/2021 | RICARDO BOHORQUEZ |
| Community Plan Implem. Overlay | Cleared | 6/15/2021 | HELEN JADALI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/6/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 10/26/2021 | Approved | JOAQUIN GREENOUGH |
| Pre-Inspection | 12/15/2021 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/27/2023 | Corrections Issued | BRENDAN MORELLI |
| Pre-Inspection | 8/7/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/23/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/31/2023 | Partial Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 10/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/19/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/19/2023 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 10/19/2023 | Approved | SCOTT FINNILA |
| HVAC-Rough | 10/19/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 10/19/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 10/19/2023 | Approved | SCOTT FINNILA |
| Wood Frame | 10/19/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 10/23/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/26/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 11/3/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/31/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/4/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |