8216 S DUNBARTON AVE 90045

Certificate Information: 8216 S DUNBARTON AVE 90045

Application / Permit
21016-10000-05050
Plan Check / Job No.
B20LA24415
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Conversion of an existing detached 2-car garage into ADU and storage. Detached ADU per state law GCS 65852.2(e)(1)(A). **COMPLY WITH DEPARTMENT ORDER effective date 01/07/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.**
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
Issued on 7/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 HELEN NGUYEN
Corrections Issued 3/12/2021 HELEN NGUYEN
Applicant returned to address corrections 4/29/2021 HELEN NGUYEN
Applicant returned to address corrections 5/31/2021 HELEN NGUYEN
Applicant returned to address corrections 1/8/2022 HELEN NGUYEN
Applicant returned to address corrections 4/15/2022 HELEN NGUYEN
Applicant returned to address corrections 5/20/2022 RICARDO RAMIREZ
Plan Check Approved 6/27/2022 JESSE JIMENEZ
Issued 7/1/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/20/2021 ANTHONY MAINEZ
Sewer availability Cleared 4/20/2021 ANTHONY MAINEZ
Specific Plan Cleared 4/28/2021 FREDDY GARCIA
Construction within easement Cleared 7/6/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 5/25/2022 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Final 12/13/2022 No Access for Inspection MARIAN PODPORA
PLUMBING-Final 12/13/2022 No Access for Inspection MARIAN PODPORA
Gas Test 12/19/2022 Partial Approval JOHN MATTILLO
PLUMBING-Final 12/19/2022 Not Ready for Inspection JOHN MATTILLO
Sewer 12/19/2022 Approved JOHN MATTILLO
Pre-Inspection 7/24/2023 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 8/4/2023 Corrections Issued ANDREW BEELI
Footing/Foundation/Slab 8/10/2023 Not Ready for Inspection ANDREW BEELI
Pre-Inspection 8/10/2023 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 8/15/2023 Partial Approval ANDREW BEELI
Pre-Inspection 8/15/2023 Approved ANDREW BEELI
Footing/Foundation/Slab 8/16/2023 Approved ANDREW BEELI
Pre-Inspection 8/16/2023 Approved ANDREW BEELI
Footing/Foundation/Slab 8/25/2023 Approved ANDREW BEELI
PLUMBING-Rough 8/29/2023 Not Ready for Inspection ANDREW BEELI
PLUMBING-Rough 9/7/2023 Approved ANDREW BEELI
Footing/Foundation/Slab 9/12/2023 Approved ANDREW BEELI
PLUMBING-Final 9/21/2023 Partial Approval ANDREW BEELI
BUILDING-Rough-Frame 9/28/2023 Not Ready for Inspection ANDREW BEELI
Green Building Rough 9/28/2023 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Rough 10/3/2023 Not Ready for Inspection ANDREW BEELI
BUILDING-Rough-Frame 10/18/2023 Partial Approval ANDREW BEELI
ELECTRICAL-Rough 10/18/2023 Approved ANDREW BEELI
Insulation 10/24/2023 Approved ANDREW BEELI
Underground Mechanical 10/24/2023 Approved ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Not Ready for Inspection ANDREW BEELI
Drywall Nailing 11/1/2023 Partial Approval ANDREW BEELI
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Approved ANDREW BEELI
Green Building Rough 11/1/2023 Not Ready for Inspection ANDREW BEELI
Rough-Elec/Plmb/HVAC 11/1/2023 Approved ANDREW BEELI
Drywall Nailing 11/7/2023 Not Ready for Inspection ANDREW BEELI
Green Building Rough 11/7/2023 Not Ready for Inspection ANDREW BEELI
Drywall Nailing 11/9/2023 Partial Approval ANDREW BEELI
Pre-Inspection 11/9/2023 Approved ANDREW BEELI
Interior/Exterior Lathing 12/12/2023 Corrections Issued ANDREW BEELI
BUILDING-Rough-Frame 1/26/2024 Not Ready for Inspection ANDREW BEELI
Drywall Nailing 1/26/2024 Conditional Approval ANDREW BEELI
Final 1/26/2024 Not Ready for Inspection ANDREW BEELI
Green Building Final 1/26/2024 Not Ready for Inspection ANDREW BEELI
Green Building Rough 1/26/2024 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 1/26/2024 Not Ready for Inspection ANDREW BEELI
BUILDING-Rough-Frame 4/4/2024 Corrections Issued ANDREW BEELI
Drywall Nailing 4/4/2024 Partial Approval ANDREW BEELI
Final 4/4/2024 Not Ready for Inspection ANDREW BEELI
Green Building Final 4/4/2024 Not Ready for Inspection ANDREW BEELI
Green Building Rough 4/4/2024 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 4/4/2024 Approved ANDREW BEELI
BUILDING-Rough-Frame 4/5/2024 Approved ANDREW BEELI
Drywall Nailing 4/5/2024 Approved ANDREW BEELI
Final 4/5/2024 Partial Approval ANDREW BEELI
Green Building Final 4/5/2024 Approved ANDREW BEELI
Green Building Rough 4/5/2024 Approved ANDREW BEELI
PLUMBING-Final 4/5/2024 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved ANDREW BEELI