1433 S 12TH AVE 90019

Certificate Information: 1433 S 12TH AVE 90019

Application / Permit
21016-10000-04984
Plan Check / Job No.
B21LA03393
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT FROM (E) GARAGE/REC. ROOM TO ADU/REC.ROOM. see comment
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 TSE MING HUANG
Corrections Issued 3/11/2021 TSE MING HUANG
Applicant returned to address corrections 11/17/2021 LUKE GONZALES
Applicant returned to address corrections 1/7/2022 SAMUEL GONZALEZ
Applicant returned to address corrections 2/20/2022 TSE MING HUANG
Plan Check Approved 2/24/2022 TSE MING HUANG
Issued 3/9/2022 APPLICANT
Building Plans Picked Up 3/14/2022 APPLICANT
CofO in Progress 11/17/2022 STUART CHAPMAN
Permit Finaled 11/30/2022 DEROLD HAUFF
CofO Issued 11/30/2022 DEROLD HAUFF
Permit Finaled 11/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/31/2021 RENZ SORIANO
Sewer availability Cleared 3/31/2021 RENZ SORIANO
Address approval Cleared 4/16/2021 RENZ SORIANO
Frnt yard landscape/Water mgmt Cleared 4/20/2021 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 6/16/2021 RENZ SORIANO
Hydrant and Access approval Cleared 11/5/2021 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 4/5/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 4/5/2022 Conditional Approval STUART CHAPMAN
Wood Frame 4/5/2022 Partial Approval STUART CHAPMAN
Deputy Wood Construction 4/7/2022 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 4/28/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 4/28/2022 Approved STUART CHAPMAN
HVAC-Rough 4/28/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/28/2022 Approved STUART CHAPMAN
Sewer 4/28/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/5/2022 Partial Approval STUART CHAPMAN
Insulation 6/1/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/1/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 6/13/2022 Approved STUART CHAPMAN
Green Building Rough 6/13/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/26/2022 Conditional Approval STUART CHAPMAN
HVAC-Rough 8/26/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/26/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 9/23/2022 Approved JULIAN AMAYA
Final 9/23/2022 Corrections Issued JULIAN AMAYA
Green Building Final 9/23/2022 Partial Inspection JULIAN AMAYA
METHANE-Final 9/23/2022 Approved JULIAN AMAYA
METHANE-Rough 9/23/2022 Approved JULIAN AMAYA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready JULIAN AMAYA
Smoke Detectors 9/23/2022 Approved JULIAN AMAYA
ELECTRICAL-Final 10/6/2022 Approved STUART CHAPMAN
Final 10/6/2022 Corrections Issued STUART CHAPMAN
Green Building Final 10/6/2022 Approved STUART CHAPMAN
HVAC-Final 10/6/2022 Approved STUART CHAPMAN
PLUMBING-Final 10/6/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved STUART CHAPMAN
Final 10/21/2022 Corrections Issued STUART CHAPMAN
Final 11/17/2022 OK to Issue CofO STUART CHAPMAN
Service/Power Release 11/17/2022 Approved STUART CHAPMAN