1821 S CARMONA AVE 90019

Certificate Information: 1821 S CARMONA AVE 90019

Application / Permit
21016-10000-04893
Plan Check / Job No.
B21LA03313
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSIONOF (E) DETACHED GARAGE INTO AN ADU GCS 65852.2 & 65852.22
Permit Issued
Issued on 12/10/2021
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 HERNAN ARREOLA
Corrections Issued 3/10/2021 HERNAN ARREOLA
Applicant returned to address corrections 5/11/2021 HERNAN ARREOLA
Plan Check Approved 5/14/2021 HERNAN ARREOLA
Issued 12/10/2021 APPLICANT
Building Plans Picked Up 12/15/2021 APPLICANT
CofO in Progress 8/31/2023 JOSE AVILA
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/16/2021 WALLIE JONG
Sewer availability Cleared 3/16/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/17/2021 WALLIE JONG

Contact Information

Architect Smith,, Carl Francis; Lic. No.: C29671 672 S AVENUE 21 # 2      LOS ANGELES, CA 90031
Contractor Vista Construction; Lic. No.: 886052-B 7541 NANCY DR      HUNTINGTON BEACH, CA 92647
Engineer Andrejic,, Milos M; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/16/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/21/2021 Partial Inspection JOSE AVILA
Underground Mechanical 12/21/2021 Approved JOSE AVILA
Footing/Foundation/Slab 12/27/2021 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 12/29/2021 Partial Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/5/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 1/5/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 1/19/2022 Approved JOSE AVILA
ELECTRICAL-Rough 8/1/2022 Approved JOSE AVILA
HVAC-Rough 8/1/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/1/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 9/23/2022 Corrections Issued JOSE AVILA
Shower Pan 9/23/2022 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 9/27/2022 Corrections Issued JOSE AVILA
Green Building Rough 9/27/2022 Not Ready for Inspection JOSE AVILA
Deputy Wood Construction 9/28/2022 Conditional Approval JOSE AVILA
Insulation 9/30/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 10/24/2022 Corrections Issued JOSE AVILA
HVAC-Rough 10/24/2022 Approved JOSE AVILA
PLUMBING-Rough 10/24/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 11/3/2022 Approved JOSE AVILA
Green Building Rough 11/3/2022 Approved JOSE AVILA
Drywall Nailing 11/16/2022 Approved STUART CHAPMAN
Insulation 11/16/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/16/2022 Approved STUART CHAPMAN
Drywall Nailing 11/21/2022 Approved MICHAEL LEWIS
Insulation 11/21/2022 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/9/2023 Partial Approval JOSE AVILA
HVAC-Final 5/9/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 5/9/2023 Corrections Issued JOSE AVILA
HVAC-Final 5/30/2023 Approved JOSE AVILA
PLUMBING-Final 5/30/2023 Approved JOSE AVILA
Green Building Final 6/8/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 6/8/2023 Approved JOSE AVILA
Final 6/28/2023 Corrections Issued JOSE AVILA
Service/Power Release 6/28/2023 Approved JOSE AVILA
Final 8/30/2023 OK to Issue CofO JOSE AVILA