1006 N WESTERN AVE A-B 90732
Certificate Information: 1006 N WESTERN AVE A-B 90732
- Application / Permit
- 21016-10000-04882
- Plan Check / Job No.
- B21LA03291
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Drive Through Fast Food
- Work Description
- SPLIT (E) RESTAURANT INTO TOW UNITS: PANDA EXPRESS + RETAIL. T.I. ONLY NO NEW FLOOR AREA. * REQUEST FOR SEPERATE ADDRESS*
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 3/7/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/14/2021 | SERGIO GUTIERREZ |
| Building Plans Picked Up | 5/17/2021 | APPLICANT |
| Issued | 12/10/2021 | APPLICANT |
| CofO in Progress | 10/21/2022 | JOEY BUCHANAN |
| CofO Issued | 10/25/2022 | DAVID TSAU |
| Permit Finaled | 10/25/2022 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2021 | ERIK BEASLEY |
| "Q" conditions | Cleared | 4/7/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | ERIK BEASLEY |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/7/2021 | DENZEL HENDERSON |
| Food establishment approval | Cleared | 5/14/2021 | LACDHS APPROVED |
Contact Information
| Architect | Wang,, Gary H; Lic. No.: C32569 | 1000 CORPORATE CENTER DR SUITE 550 MONTEREY PARK, CA 91754 |
| Contractor | Rockwall Construction Company; Lic. No.: 777138-B | 4345 E LOWELL STREET SUITE H ONTARIO, CA 91761 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2022 | Partial Approval | DAVID TSAU |
| Pre-Inspection | 3/11/2022 | Corrections Issued | JOEY BUCHANAN |
| Green Building Rough | 3/25/2022 | Approved | DAVID TSAU |
| Wood Frame | 3/25/2022 | Partial Approval | DAVID TSAU |
| Insulation | 4/14/2022 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 4/22/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/27/2022 | Conditional Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/29/2022 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 5/18/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 5/24/2022 | Not Ready for Inspection | DAVID TSAU |
| Partition/T-Bar Ceiling | 6/7/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Interior/Exterior Lathing | 6/8/2022 | Approved | JOEY BUCHANAN |
| Final | 9/16/2022 | Corrections Issued | JOEY BUCHANAN |
| Green Building Final | 9/16/2022 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 9/16/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 9/16/2022 | Approved | JOEY BUCHANAN |
| Final | 9/22/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 9/27/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 10/21/2022 | OK to Issue CofO | JOEY BUCHANAN |