977 N NORTH BROADWAY 90012
Certificate Information: 977 N NORTH BROADWAY 90012
- Application / Permit
- 21016-10000-04823
- Plan Check / Job No.
- B21LA03261
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Voluntary seismic strengthening of selective deficient elements of the steel moment frame superstructure only (the retrofit conform to requirement of LAEBC section 503.13 items 1 to 4 only)
- Permit Issued
- Issued on 8/10/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/2/2022
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SUEN LIEU |
| Corrections Issued | 3/18/2021 | SUEN LIEU |
| Quality Review Completed | 3/24/2021 | CHARLES CHANG |
| Building Plans Picked Up | 3/25/2021 | APPLICANT |
| Applicant returned to address corrections | 5/11/2021 | SUEN LIEU |
| Applicant returned to address corrections | 7/21/2021 | SUEN LIEU |
| Plan Check Approved | 8/3/2021 | SUEN LIEU |
| Issued | 8/10/2021 | APPLICANT |
| Permit Finaled | 2/1/2022 | MARK FERRARI |
Permit Application Clearance Information
| ZI | Cleared | 8/2/2021 | DAVID URITA |
Contact Information
| Contractor | Corporate Contractors Inc; Lic. No.: 604407-B | 2550 CORPORATE PL STE C-111 MONTEREY PARK, CA 91754 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 9/28/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 9/29/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 9/30/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/1/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 10/4/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/5/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/6/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/7/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/8/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 10/12/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/13/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/14/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/15/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 10/18/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/19/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/20/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/21/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/22/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/25/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/26/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/27/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/28/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/29/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/1/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/2/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/3/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/4/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/5/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/8/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/9/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/10/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/12/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/15/2021 | Approved | MARK FERRARI |
| Pre-Inspection | 11/15/2021 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/16/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/17/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/18/2021 | No Result Entered | RONALD PACHECO |
| Deputy Steel/Welding | 11/19/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/22/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Fireproofing | 11/23/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/23/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/24/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/29/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/30/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/1/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/2/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 12/3/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 12/6/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 12/7/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 12/7/2021 | Partial Approval | MARK FERRARI |
| Structural Steel Frame | 12/7/2021 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/8/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/9/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/10/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/13/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 12/14/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/15/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/16/2021 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 12/16/2021 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 12/17/2021 | Conditional Approval | MARK FERRARI |
| Deputy Fireproofing | 12/20/2021 | Conditional Approval | MARK FERRARI |
| Drywall Nailing | 12/30/2021 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 1/19/2022 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 1/26/2022 | Approved | MARK FERRARI |
| Structural Steel Frame | 1/26/2022 | Approved | MARK FERRARI |
| Final | 2/1/2022 | Permit Finaled | MARK FERRARI |
| Green Building Final | 2/1/2022 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 2/1/2022 | Approved | MARK FERRARI |