321 N VAN NESS AVE 90004
Certificate Information: 321 N VAN NESS AVE 90004
- Application / Permit
- 21016-10000-04718
- Plan Check / Job No.
- B21LA03185
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- e-plan: PROPOSED INTERIOR REMODEL TO EXISTING SFD, DEMO INTEIRIOR WALLS, WINDOW/DOOR CHANGEOUT, VAULATED CEILING, BATHROOM/KITCHEN REMODEL.
- Permit Issued
- Issued on 5/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/3/2022
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | MICHAEL LOPEZ |
| Corrections Issued | 3/22/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 3/29/2021 | HERNAN ARREOLA |
| Plan Check Approved | 4/26/2021 | MICHAEL LOPEZ |
| Issued | 5/4/2021 | APPLICANT |
| Permit Finaled | 3/2/2022 | ARTHUR SARGSYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | 20301 VENTURA BLVD #222 WOODLAND HILLS, CA 91364 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: NA5266 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/3/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 9/3/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 9/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 9/8/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/14/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/20/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 9/27/2021 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 10/1/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/14/2021 | Approved | ARTHUR SARGSYAN |
| Final | 3/2/2022 | Permit Finaled | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/2/2022 | Approved | ARTHUR SARGSYAN |