13180 W KELOWNA ST 91331
Certificate Information: 13180 W KELOWNA ST 91331
- Application / Permit
- 21016-10000-04695
- Plan Check / Job No.
- B21LA03172
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/21/2021
- Issuing Office
- Metro
- Current Status
- Issued on 5/21/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | KEVIN MORALES |
| Corrections Issued | 3/10/2021 | KEVIN MORALES |
| Plan Check Approved | 4/9/2021 | KEVIN MORALES |
| Issued | 5/21/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/12/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 3/16/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2021 | ADRIAN CASTRO |
| Clean Up Green Up | Cleared | 3/25/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/18/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/18/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 1/18/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 1/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/18/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/4/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/4/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/4/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 2/4/2022 | Partial Approval | MICHEL ABAJAN |
| Insulation | 2/16/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/1/2022 | Approved | MICHEL ABAJAN |
| Final | 4/11/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/11/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/11/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 4/11/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/13/2022 | Approved | MICHEL ABAJAN |
| Final | 4/13/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/13/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/13/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/13/2022 | Approved | MICHEL ABAJAN |