22741 W VICTORY BLVD 91307
Certificate Information: 22741 W VICTORY BLVD 91307
- Application / Permit
- 21016-10000-04648
- Plan Check / Job No.
- B21LA03136
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- TENANT IMPROVEMENT TO CONVERT HARDWARE STORE TO FOOD MARKET (21915 sf) INCLUDING PARTIAL NEW INTERIOR CONCRETE FLOOR SLAB, NEW FACADE REMODEL AND NEW STOREFRONTS. NEW ROOFTOP UNITS. INSTALL OF NEW COOLER AND FREEZER BOX & EQUIPMENT. PARTIAL SITE IMPROVEMENTS INCLUDING FRONT WALKWAY MODIFICATION AND NEW ACCESSIBLE RAMPS; ADDITION OF TRASH ENCLOSURE 14.1' x 19'
- Permit Issued
- Issued on 8/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2021 | SINA KHOSRAVI |
| Corrections Issued | 3/17/2021 | SINA KHOSRAVI |
| Quality Review Completed | 3/30/2021 | STANLEY RAAP |
| Disabled Access Plans Picked Up | 3/31/2021 | APPLICANT |
| Applicant returned to address corrections | 5/6/2021 | SINA KHOSRAVI |
| Green Plans Picked Up | 5/26/2021 | APPLICANT |
| Applicant returned to address corrections | 6/17/2021 | SINA KHOSRAVI |
| Plan Check Approved | 7/19/2021 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/20/2021 | APPLICANT |
| Issued | 8/5/2021 | APPLICANT |
| CofO in Progress | 8/24/2022 | CAMERON CHABAN |
| Permit Finaled | 1/4/2023 | JEFFREY DURAN |
| CofO Issued | 1/4/2023 | JEFFREY DURAN |
| Permit Finaled | 1/4/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 5/5/2021 | MARITZA PRZEKOP |
| ZA Case | Cleared | 5/5/2021 | MARITZA PRZEKOP |
| ZA Case | Cleared | 5/5/2021 | MARITZA PRZEKOP |
| Green Code | Cleared | 5/6/2021 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 5/7/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/17/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/18/2021 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 6/3/2021 | SINA KHOSRAVI |
| Food establishment approval | Cleared | 6/18/2021 | LACDHS APPROVED |
Contact Information
| Architect | Williams,, Bradley James; Lic. No.: C30604 | 3091 ARMOURDALE AVENUE LONG BEACH, CA 90808 |
| Contractor | Grant Rc Jv; Lic. No.: 1057040-B | 1545 FARADAY AVE STE 101 CARLSBAD, CA 92008 |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
| Engineer | Sehatzadeh,, Bahareh; Lic. No.: C89859 | 30 EXECUTIVE PARK SUITE 100 IRVINE, CA 92614 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 10/19/2021 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/21/2021 | Partial Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 10/22/2021 | Conditional Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 10/22/2021 | Not Ready for Inspection | ALAN NOVAK |
| Drywall Nailing | 12/2/2021 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 1/25/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 1/26/2022 | Approved | DANIEL VARNUM |
| Deputy Reinf. Masonry | 2/2/2022 | Conditional Approval | DANIEL VARNUM |
| Green Building Rough | 2/3/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Masonry Wall/Backfill | 2/3/2022 | Partial Approval | DANIEL VARNUM |
| Reinforced Masonry Frame | 2/3/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Masonry | 2/10/2022 | Conditional Approval | ANDREW DORSO |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Reinforced Masonry Frame | 2/10/2022 | Partial Approval | DANIEL VARNUM |
| Masonry Wall/Backfill | 2/18/2022 | Approved | CAMERON CHABAN |
| Light Gage Steel Frame | 2/22/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 2/23/2022 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 2/23/2022 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 2/24/2022 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 2/25/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 3/3/2022 | Partial Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 3/3/2022 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 3/4/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Drywall Nailing | 3/7/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/8/2022 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Approved | DANIEL VARNUM |
| Grading Pre-Inspection | 3/16/2022 | Partial Inspection | CAMERON CHABAN |
| Light Gage Steel Frame | 4/18/2022 | Conditional Approval | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | KENNETH ROBERTS |
| Insulation | 4/22/2022 | Partial Approval | DANNY RODRIGUEZ |
| Interior/Exterior Lathing | 4/27/2022 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/28/2022 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 5/2/2022 | Approved | CAMERON CHABAN |
| T-Bar Ceiling | 5/6/2022 | Partial Approval | DANIEL VARNUM |
| T-Bar Ceiling | 5/17/2022 | Approved | DANIEL VARNUM |
| Final | 6/17/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Green Building Final | 6/17/2022 | Partial Inspection | CAMERON CHABAN |
| Green Building Rough | 6/17/2022 | Approved | CAMERON CHABAN |
| Reinforced Masonry Frame | 6/17/2022 | Approved | CAMERON CHABAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | CAMERON CHABAN |
| Smoke Detectors | 6/17/2022 | Approved | CAMERON CHABAN |
| Special/Order Compliance | 8/11/2022 | Approved | CAMERON CHABAN |
| Final | 8/17/2022 | Partial Inspection | CAMERON CHABAN |
| Green Building Final | 8/17/2022 | Approved | CAMERON CHABAN |
| Special/Order Compliance | 8/19/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 8/23/2022 | OK to Issue CofO | CAMERON CHABAN |