20155-20157 W HARTLAND ST 91306

Certificate Information: 20155-20157 W HARTLAND ST 91306

Application / Permit
21016-10000-04419
Plan Check / Job No.
B21LA03027
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 9/16/2021
Issuing Office
Current Status
CofO Issued on 8/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2021 APPLICANT
Assigned to Plan Check Engineer 2/19/2021 KEVIN MORALES
Corrections Issued 2/19/2021 KEVIN MORALES
Plan Check Approved 9/13/2021 KEVIN MORALES
Issued 9/16/2021 APPLICANT
CofO in Progress 8/18/2022 STEVEN BACK
Permit Finaled 8/22/2022 JOHN JANSON
CofO Issued 8/22/2022 JOHN JANSON
Permit Finaled 8/22/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/23/2021 GABRIEL ROBLES
Sewer availability Cleared 3/23/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/24/2021 GABRIEL ROBLES
ZI Cleared 8/31/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/26/2022 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 1/31/2022 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 1/31/2022 Approved STEVEN BACK
PLUMBING-Rough 2/15/2022 Partial Approval STEVEN BACK
Footing/Foundation/Slab 4/29/2022 Approved STEVEN BACK
PLUMBING-Rough 4/29/2022 Corrections Issued STEVEN BACK
Sewer 4/29/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 5/10/2022 Corrections Issued STEVEN BACK
Green Building Rough 5/10/2022 Approved STEVEN BACK
HVAC-Rough 5/10/2022 Approved STEVEN BACK
PLUMBING-Rough 5/10/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 5/11/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 No Access for Inspection STEVEN BACK
Footing/Foundation/Slab 6/2/2022 Corrections Issued JEFFREY PARD
BUILDING-Rough-Frame 6/8/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 6/27/2022 Approved STEVEN BACK
Insulation 6/27/2022 Approved STEVEN BACK
Interior/Exterior Lathing 6/27/2022 Partial Approval STEVEN BACK
Shower Pan 6/27/2022 Approved STEVEN BACK
Drywall Nailing 7/6/2022 Approved JESUS PINEDA
Final 8/2/2022 Corrections Issued JEFFREY BULL
Green Building Final 8/2/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 8/2/2022 Approved JEFFREY BULL
Final 8/9/2022 Corrections Issued STEVEN BACK
Green Building Final 8/9/2022 Approved STEVEN BACK
Final 8/18/2022 OK to Issue CofO STEVEN BACK