3806 1/4 S MAPLE AVE 90011
Certificate Information: 3806 1/4 S MAPLE AVE 90011
- Application / Permit
- 21016-10000-04414
- Plan Check / Job No.
- B21LA03024
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADU apartment conversion. Convert Existing detached single car garage into a new ADU studio.
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 1/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2021 | JOE VO |
| Corrections Issued | 2/22/2021 | JOE VO |
| Plan Check Approved | 3/16/2021 | JOE VO |
| Issued | 5/7/2021 | APPLICANT |
| CofO in Progress | 1/31/2023 | ALAN MORELOS |
| CofO Issued | 1/31/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/31/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/26/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 3/5/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/15/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 3/1/2022 | Approved | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 3/8/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 3/8/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 3/8/2022 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 4/29/2022 | Approved | TIMOTHY BUXTON |
| Insulation | 5/11/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 5/17/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 5/17/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/23/2022 | Approved | JAMES POWERS |
| Final | 9/16/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 9/16/2022 | Approved | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 9/16/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 10/6/2022 | Not Ready for Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 10/6/2022 | Approved | GREGORY POMISH |
| Final | 11/1/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 1/17/2023 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 1/18/2023 | No Access for Inspection | ALFREDO LOPEZ |
| Final | 1/26/2023 | Conditional Approval | ALAN MORELOS |
| Final | 1/31/2023 | OK to Issue CofO | ALAN MORELOS |