1513 W OAK GROVE DR 90041

Certificate Information: 1513 W OAK GROVE DR 90041

Application / Permit
21016-10000-04404
Plan Check / Job No.
B21LA03020
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2021 APPLICANT
Assigned to Plan Check Engineer 2/23/2021 KEVIN MORALES
Corrections Issued 2/23/2021 KEVIN MORALES
Applicant returned to address corrections 4/26/2021 KEVIN MORALES
Applicant returned to address corrections 5/27/2021 KEVIN MORALES
Plan Check Approved 6/10/2021 KEVIN MORALES
Issued 6/16/2021 APPLICANT
CofO in Progress 7/30/2022 CRAIG VAUGHAN
CofO in Progress 7/30/2022 CRAIG VAUGHAN
Permit Finaled 8/11/2022 DEROLD HAUFF
CofO Issued 8/11/2022 DEROLD HAUFF
Permit Finaled 8/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/27/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/27/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 4/27/2021 WALLIE JONG
Sewer availability Cleared 4/27/2021 WALLIE JONG
Grading Pre-Inspection Cleared 6/8/2021 KIRK LINKLATER

Contact Information

Contractor S & J Building Brothers Inc; Lic. No.: 1043846-B 5908 1/2 EASTON ST      LOS ANGELES, CA 90022
Engineer Eden,, Joseph Taki; Lic. No.: C39955 14412 FRIAR ST      VAN NUYS, CA 91401

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/18/2021 Approved COREY HUPP
Excavation/Setback/Form/Re-Bar 6/24/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/24/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 7/15/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/20/2021 Partial Approval CRAIG VAUGHAN
Sewer 7/20/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 8/11/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 8/11/2021 Approved CRAIG VAUGHAN
Green Building Rough 8/11/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 8/11/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/18/2021 Partial Inspection SCOTT FINNILA
Rough-Elec/Plmb/HVAC 8/18/2021 Corrections Issued SCOTT FINNILA
Insulation 8/20/2021 Corrections Issued JUSTIN CURTIS
Interior/Exterior Lathing 8/20/2021 Approved JUSTIN CURTIS
Drywall Nailing 8/30/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/1/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/1/2021 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 9/1/2021 Approved CRAIG VAUGHAN
HVAC-Rough 9/1/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/1/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 10/18/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 10/18/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 10/18/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 11/22/2021 Approved CRAIG VAUGHAN
HVAC-Final 11/22/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 11/22/2021 Approved CRAIG VAUGHAN
Green Building Final 11/23/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 11/23/2021 Approved CRAIG VAUGHAN
Drywall Nailing 4/15/2022 Approved CRAIG VAUGHAN
Final 4/15/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/15/2022 Approved CRAIG VAUGHAN
Verify Rec and Parks Fee Memo 4/15/2022 Approved CRAIG VAUGHAN
Final 7/29/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 7/29/2022 Approved CRAIG VAUGHAN