5737 E ALDAMA ST 90042
Certificate Information: 5737 E ALDAMA ST 90042
- Application / Permit
- 21016-10000-04401
- Plan Check / Job No.
- B21LA03018
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 18'-4" x 18'-9" detached garage into an ADU.
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2021 | JOE VO |
| Corrections Issued | 2/23/2021 | JOE VO |
| Applicant returned to address corrections | 11/3/2021 | JOE VO |
| Plan Check Approved | 11/12/2021 | JOE VO |
| Issued | 12/6/2021 | APPLICANT |
| CofO in Progress | 8/13/2022 | AMY COLIN |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/4/2021 | ROSA SILVA |
| HPOZ | Cleared | 10/8/2021 | KATIE DEBIASE |
| Historic monument | Cleared | 10/8/2021 | KATIE DEBIASE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/15/2022 | Partial Inspection | AMY COLIN |
| Green Building Rough | 3/15/2022 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 5/3/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 5/3/2022 | Approved | AMY COLIN |
| Footing/Foundation/Slab | 5/3/2022 | Approved | AMY COLIN |
| Green Building Rough | 5/3/2022 | Approved | AMY COLIN |
| HVAC-Rough | 5/3/2022 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 5/3/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 5/3/2022 | Approved | AMY COLIN |
| Shower Pan | 5/3/2022 | Approved | AMY COLIN |
| Insulation | 5/25/2022 | Approved | AMY COLIN |
| Drywall Nailing | 6/6/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 6/24/2022 | Partial Inspection | AMY COLIN |
| Pre-Inspection | 6/24/2022 | Approved | AMY COLIN |
| Final | 7/22/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 7/22/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Not Required | AMY COLIN |
| Smoke Detectors | 7/22/2022 | Approved | AMY COLIN |
| Final | 7/28/2022 | Partial Approval | AMY COLIN |
| Special/Order Compliance | 7/28/2022 | Approved | AMY COLIN |
| Final | 8/13/2022 | OK to Issue CofO | AMY COLIN |