743 1/2 E 113TH ST 90059

Certificate Information: 743 1/2 E 113TH ST 90059

Application / Permit
21016-10000-04309
Plan Check / Job No.
B21LA02925
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING (E) DETACHED GARAGE INTO AN ADU.
Permit Issued
Issued on 11/20/2021
Issuing Office
Current Status
CofO Issued on 7/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2021 APPLICANT
Assigned to Plan Check Engineer 3/1/2021 RICARDO RAMIREZ
Corrections Issued 3/1/2021 RICARDO RAMIREZ
Plan Check Approved 6/11/2021 FERNANDO FLORES
Issued 11/20/2021 APPLICANT
Building Plans Picked Up 12/1/2021 APPLICANT
CofO in Progress 6/28/2023 JOHN KLARIN
Permit Finaled 7/10/2023 ANSON MAGLASANG
CofO Issued 7/10/2023 ANSON MAGLASANG
Permit Finaled 7/10/2023 ANSON MAGLASANG

Permit Application Clearance Information

Sewer availability Cleared 3/5/2021 JEANIE LAM
Hydrant and Access approval Cleared 4/23/2021 KURT CORRAL
Address approval Cleared 5/17/2021 JEANIE LAM
Construction near power lines Cleared 6/5/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 6/15/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/3/2022 Corrections Issued JOHN KLARIN
Deputy Drilled-In Anchors 3/23/2022 Approved JOHN KLARIN
Deputy Other (see comments) 3/23/2022 Approved JOHN KLARIN
PLUMBING-Rough 4/6/2022 Approved ALEJANDRO DE ARTOLA
Wood Frame 8/29/2022 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 12/6/2022 Approved JOHN KLARIN
HVAC-Rough 12/6/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 12/6/2022 Approved JOHN KLARIN
PLUMBING-Rough 12/6/2022 Approved JOHN KLARIN
Wood Frame 12/6/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 12/8/2022 Approved JOHN KLARIN
Gas Test 12/8/2022 Approved JOHN KLARIN
HVAC-Rough 12/8/2022 Approved JOHN KLARIN
Insulation 12/8/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 12/8/2022 Approved JOHN KLARIN
Drywall Nailing 12/14/2022 Approved JOHN KLARIN
Gas Test 2/10/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/28/2023 Approved JAMES CHAVEZ
Final 4/28/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/28/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 4/28/2023 Not Ready for Inspection JAMES CHAVEZ
Pre-Inspection 5/25/2023 Approved JOHN KLARIN
Pre-Inspection 5/31/2023 Corrections Issued JOHN KLARIN
Pre-Inspection 6/5/2023 Corrections Issued JOHN KLARIN
Pre-Inspection 6/21/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 6/27/2023 Approved JOHN KLARIN
Final 6/27/2023 OK to Issue CofO JOHN KLARIN
HVAC-Final 6/27/2023 Approved JOHN KLARIN
PLUMBING-Final 6/27/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 6/27/2023 Approved JOHN KLARIN