15921 W DEVONSHIRE ST 91344
Certificate Information: 15921 W DEVONSHIRE ST 91344
- Application / Permit
- 21016-10000-04295
- Plan Check / Job No.
- B21LA02915
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Covert existing detached garage to new accessory dwelling unit ADU per Type V sheet. AND PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 11/30/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2021 | CARLOS MONTES |
| Corrections Issued | 3/3/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 10/18/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 11/2/2021 | CARLOS MONTES |
| Plan Check Approved | 11/16/2021 | CARLOS MONTES |
| Issued | 11/30/2021 | APPLICANT |
| CofO in Progress | 9/2/2022 | JENNIFER RABUCHIN |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/4/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Ground Up Builders And Design Inc; Lic. No.: 911849-B | 14545 VICTORY BLVD STE 601 VAN NUYS, CA 91411 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 12/28/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/28/2021 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 12/28/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/4/2022 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 1/4/2022 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 1/4/2022 | Not Ready for Inspection | MARK JOHNSON |
| Deputy Drilled-In Anchors | 1/12/2022 | Approved | MARK JOHNSON |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 1/12/2022 | Partial Approval | MARK JOHNSON |
| Sewer | 1/12/2022 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 1/26/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Gas Test | 1/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/26/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/4/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/4/2022 | Approved | JESUS RODRIGUEZ |
| Gas Test | 2/4/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 2/4/2022 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/4/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| Insulation | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Not Ready | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/4/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 3/4/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 3/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/16/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 3/16/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 3/16/2022 | Approved | RAUL OLAGI |
| Insulation | 3/16/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/16/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/22/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 4/1/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/7/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/15/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/15/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/15/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/15/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/15/2022 | Approved | JENNIFER RABUCHIN |