1910 S HOLMBY AVE 90025
Certificate Information: 1910 S HOLMBY AVE 90025
- Application / Permit
- 21016-10000-04270
- Plan Check / Job No.
- B21LA02903
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install (3) Special Steel Cantilever Columns
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- CofC Issued on 8/16/2021
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2021 | HANS SANTIAGO |
| Corrections Issued | 3/1/2021 | HANS SANTIAGO |
| Quality Review Completed | 3/3/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/17/2021 | HANS SANTIAGO |
| Plan Check Approved | 3/22/2021 | ANDREW SANTIAGO |
| Issued | 6/7/2021 | APPLICANT |
| OK for CofC | 8/16/2021 | GRANT WOODS |
| CofC Issued | 8/16/2021 | TED RIES |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/2/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2021 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 6/14/2021 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 6/15/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Not Ready | GRANT WOODS |
| Structural Steel Frame | 6/15/2021 | Approved | GRANT WOODS |
| Wood Frame | 6/15/2021 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 6/16/2021 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 6/16/2021 | Conditional Approval | GRANT WOODS |
| Insulation | 6/18/2021 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 7/2/2021 | Approved | PAUL DAVIDSON |
| Final | 8/11/2021 | Partial Inspection | GRANT WOODS |
| METHANE-Final | 8/11/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/11/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 8/11/2021 | Approved | GRANT WOODS |
| Final | 8/16/2021 | OK for CofC | GRANT WOODS |