460 S HIGHLAND AVE 90036

Certificate Information: 460 S HIGHLAND AVE 90036

Application / Permit
21016-10000-04213
Plan Check / Job No.
B21LA02865
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE (442SF ZONING) TO ACCESSORY DWELLING UNIT PER WFPP (Conversion of Accessory Building per State Law, CA Govt. Code 65852.2(e)(1)(A)) "COMPLY WITH DEPARTMENT ORDER effective date 02/19/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 AUNG SOE
Corrections Issued 3/8/2021 AUNG SOE
Applicant returned to address corrections 5/18/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 5/20/2021 APPLICANT
Plan Check Approved 8/13/2021 AUNG SOE
Issued 11/9/2021 APPLICANT
CofO in Progress 10/18/2022 JULIAN AMAYA
CofO in Progress 10/19/2022 JULIAN AMAYA
Permit Finaled 10/29/2022 DEROLD HAUFF
CofO Issued 10/29/2022 DEROLD HAUFF
Permit Finaled 10/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/18/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 3/18/2021 RENZ SORIANO
Sewer availability Cleared 3/18/2021 RENZ SORIANO
CPC Cleared 4/15/2021 ANACANY HURTADO
CPC Cleared 4/15/2021 ANACANY HURTADO
CPC Cleared 4/15/2021 ANACANY HURTADO
HPOZ Cleared 5/7/2021 SUKI GERSHENHORN
Historic monument Cleared 5/7/2021 SUKI GERSHENHORN

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Ben Porat Moshe M; Lic. No.: 963181-B P O BOX 48603      LOS ANGELES, CA 90048

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/11/2022 Partial Approval CRAIG DAVIS
METHANE-Final 2/11/2022 Not Ready for Inspection CRAIG DAVIS
METHANE-Rough 2/11/2022 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 2/11/2022 Corrections Issued CRAIG DAVIS
Drywall Nailing 3/11/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 3/11/2022 Approved ARTHUR SARGSYAN
Sewer 3/11/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Not Ready ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/13/2022 Approved ARTHUR SARGSYAN
Final 4/13/2022 Conditional Approval ARTHUR SARGSYAN
METHANE-Final 4/13/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 4/13/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/13/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 4/13/2022 Approved ARTHUR SARGSYAN
Final 8/11/2022 Partial Inspection JULIAN AMAYA
Final 10/13/2022 OK to Issue CofO JULIAN AMAYA