980 W 190TH ST UNIT B1 90502
Certificate Information: 980 W 190TH ST UNIT B1 90502
- Application / Permit
- 21016-10000-04165
- Plan Check / Job No.
- B21LA02815
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM RETAIL TO COFFEE SHOP (RESTAURANT). ENTERPRISE ZONE THEREFORE NO CHANGE IN PARKING.
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2021 | STANLEY RAAP |
| Corrections Issued | 3/2/2021 | STANLEY RAAP |
| Applicant returned to address corrections | 6/28/2021 | RACHEL BEYENE |
| Plan Check Approved | 7/8/2021 | RAHEL BEYENE |
| Issued | 8/11/2021 | APPLICANT |
| Building Plans Picked Up | 8/25/2021 | APPLICANT |
| CofO in Progress | 4/4/2023 | JOEY BUCHANAN |
| CofO in Progress | 4/4/2023 | JOEY BUCHANAN |
| Permit Finaled | 4/5/2023 | DAVID TSAU |
| CofO Issued | 4/5/2023 | DAVID TSAU |
| Permit Finaled | 4/5/2023 | DAVID TSAU |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/1/2021 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2021 | CHINH DINH |
| Sewer availability | Cleared | 4/5/2021 | CHINH DINH |
| Food Service Establishment | Cleared | 5/18/2021 | JASH PATEL |
| Food establishment approval | Cleared | 8/10/2021 | LACDHS APPROVED |
Contact Information
| Contractor | La La Construction Inc; Lic. No.: 1076071-B | 2032 CONTESSA IRVINE, CA 92620 |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 255 W 5TH ST APT 706 SAN PEDRO, CA 90731 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/1/2021 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 12/13/2021 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 12/13/2021 | Conditional Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 1/12/2022 | Approved | JOEY BUCHANAN |
| Final | 10/31/2022 | No Access for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/31/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 10/31/2022 | Approved | JOEY BUCHANAN |
| Pre-Inspection | 11/1/2022 | Corrections Issued | JOEY BUCHANAN |
| Final | 3/1/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 4/4/2023 | OK to Issue CofO | JOEY BUCHANAN |