- 1. RELOCATE SUMP PUMP AT BACK PROPERTY. 2. REMOVE MAIN HOUSE CHIMNEY AND ADD A SLIDING DOOR 11'-9" WIDE.
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/5/2023
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 2/17/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/18/2021 | FARUK SEZER |
| Applicant returned to address corrections | 8/11/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 9/30/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/27/2021 | SERGIO GUTIERREZ |
| Issued | 12/9/2021 | APPLICANT |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| Permit Finaled | 4/4/2023 | BRENDAN LOONEY |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | A G Builders & Development Corp; Lic. No.: 959503-B | 5530 CORBIN AVE SUITE #250 TARZANA, CA 91356 |
| Engineer | Lee,, Jack C; Lic. No.: L8407 | 576 E LAMBERT RD BREA, CA 92821 |
| Engineer | Sin,, John P; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2022 | Not Ready for Inspection | ANDREW NAVE |
| Deputy Drilled-In Anchors | 7/19/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/21/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/25/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/25/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/4/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 8/8/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/9/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 8/11/2022 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 3/31/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/4/2023 | Approved | BRENDAN LOONEY |
| Final | 4/4/2023 | Permit Finaled | BRENDAN LOONEY |
| HVAC-Final | 4/4/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 4/4/2023 | Approved | BRENDAN LOONEY |