14674-14676 W REX ST 91342
Certificate Information: 14674-14676 W REX ST 91342
- Application / Permit
- 21016-10000-04011
- Plan Check / Job No.
- B21LA02708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) ATT GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.22. ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 2/16/2021 | APPLICANT |
Assigned to Plan Check Engineer | 2/18/2021 | LAMAR DAVIS |
Corrections Issued | 2/18/2021 | LAMAR DAVIS |
Applicant returned to address corrections | 3/9/2021 | CARLOS MONTES |
Plan Check Approved | 4/29/2021 | CARLOS MONTES |
Issued | 4/30/2021 | APPLICANT |
CofO in Progress | 10/22/2021 | JOHN HAYES |
CofO Issued | 11/22/2021 | MICHAEL SMITH |
Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Building Plans Picked Up | 3/30/2022 | APPLICANT |
Permit Application Clearance Information
Miscellaneous | Cleared | 2/23/2021 | LAMAR DAVIS |
Address approval | Cleared | 3/5/2021 | ADRIAN CASTRO |
Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | ADRIAN CASTRO |
Sewer availability | Cleared | 3/5/2021 | ADRIAN CASTRO |
Miscellaneous | Cleared | 4/7/2021 | LAMAR DAVIS |
Contact Information
Contractor | Owner-Builder | , |
Inspector Information
KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Deputy Drilled-In Anchors | 5/7/2021 | Conditional Approval | MICHAEL TEMPLE |
Footing/Foundation/Slab | 5/7/2021 | Corrections Issued | KIM BEAUCHAMP |
PLUMBING-Rough | 5/7/2021 | Approved | KIM BEAUCHAMP |
BUILDING-Rough-Frame | 5/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
ELECTRICAL-Rough | 5/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
Footing/Foundation/Slab | 5/13/2021 | Approved | MISAEL ESPARZA |
ELECTRICAL-Rough | 6/1/2021 | Corrections Issued | MISAEL ESPARZA |
BUILDING-Rough-Frame | 6/2/2021 | Partial Approval | MISAEL ESPARZA |
Gas Test | 6/2/2021 | Approved | MISAEL ESPARZA |
Interior/Exterior Lathing | 6/16/2021 | Corrections Issued | DEANDRE HOFFMAN |
ELECTRICAL-Rough | 6/23/2021 | Conditional Approval | MISAEL ESPARZA |
Interior/Exterior Lathing | 6/23/2021 | Partial Approval | MISAEL ESPARZA |
BUILDING-Rough-Frame | 7/1/2021 | Partial Approval | JOHN HAYES |
Green Building Rough | 7/1/2021 | Not Ready for Inspection | JOHN HAYES |
HVAC-Rough | 7/1/2021 | Not Ready for Inspection | JOHN HAYES |
HVAC-Rough | 7/12/2021 | Corrections Issued | MISAEL ESPARZA |
Insulation | 7/12/2021 | Partial Approval | MISAEL ESPARZA |
BUILDING-Rough-Frame | 7/15/2021 | Approved | MISAEL ESPARZA |
ELECTRICAL-Rough | 7/15/2021 | Approved | MISAEL ESPARZA |
Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | MISAEL ESPARZA |
HVAC-Rough | 7/15/2021 | Approved | MISAEL ESPARZA |
Insulation | 7/15/2021 | Approved | MISAEL ESPARZA |
Shower Pan | 7/15/2021 | Approved | MISAEL ESPARZA |
Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Approved | ARTHUR SARGSYAN |
Interior/Exterior Lathing | 7/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
Drywall Nailing | 7/22/2021 | Partial Approval | DEANDRE HOFFMAN |
Interior/Exterior Lathing | 7/22/2021 | Partial Approval | DEANDRE HOFFMAN |
Drywall Nailing | 7/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
Interior/Exterior Lathing | 7/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
BUILDING-Rough-Frame | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
ELECTRICAL-Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
Final | 9/23/2021 | Corrections Issued | JOHN HAYES |
Green Building Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
Green Building Rough | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
HVAC-Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
PLUMBING-Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | JOHN HAYES |
Service/Power Release | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
Smoke Detectors | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
ELECTRICAL-Final | 9/30/2021 | Not Ready for Inspection | JOHN HAYES |
HVAC-Final | 9/30/2021 | Not Ready for Inspection | JOHN HAYES |
PLUMBING-Final | 9/30/2021 | Not Ready for Inspection | JOHN HAYES |
BUILDING-Rough-Frame | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
ELECTRICAL-Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
Green Building Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
Green Building Rough | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
HVAC-Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
PLUMBING-Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Not Ready | JOHN HAYES |
Smoke Detectors | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
BUILDING-Rough-Frame | 10/21/2021 | Approved | JOHN HAYES |
ELECTRICAL-Final | 10/21/2021 | Approved | JOHN HAYES |
Final | 10/21/2021 | OK to Issue CofO | JOHN HAYES |
Green Building Final | 10/21/2021 | Approved | JOHN HAYES |
Green Building Rough | 10/21/2021 | Approved | JOHN HAYES |
HVAC-Final | 10/21/2021 | Approved | JOHN HAYES |
PLUMBING-Final | 10/21/2021 | Approved | JOHN HAYES |
SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | JOHN HAYES |
Smoke Detectors | 10/21/2021 | Approved | JOHN HAYES |