14674-14676 W REX ST 91342
Certificate Information: 14674-14676 W REX ST 91342
- Application / Permit
- 21016-10000-04011
- Plan Check / Job No.
- B21LA02708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePLAN CHECK* CONVERSION OF (E) ATT GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.22. ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | LAMAR DAVIS |
| Corrections Issued | 2/18/2021 | LAMAR DAVIS |
| Applicant returned to address corrections | 3/9/2021 | CARLOS MONTES |
| Plan Check Approved | 4/29/2021 | CARLOS MONTES |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 10/22/2021 | JOHN HAYES |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/23/2021 | LAMAR DAVIS |
| Address approval | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 4/7/2021 | LAMAR DAVIS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/7/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 5/7/2021 | Corrections Issued | KIM BEAUCHAMP |
| PLUMBING-Rough | 5/7/2021 | Approved | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 5/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/13/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/1/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/2/2021 | Partial Approval | MISAEL ESPARZA |
| Gas Test | 6/2/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/16/2021 | Corrections Issued | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/23/2021 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/23/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/1/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 7/1/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/1/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/12/2021 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 7/12/2021 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/15/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/15/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 7/15/2021 | Approved | MISAEL ESPARZA |
| Insulation | 7/15/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 7/15/2021 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 7/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Drywall Nailing | 7/22/2021 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/22/2021 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 7/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/23/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 9/30/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 9/30/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 9/30/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/5/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/21/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 10/21/2021 | Approved | JOHN HAYES |
| Final | 10/21/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 10/21/2021 | Approved | JOHN HAYES |
| Green Building Rough | 10/21/2021 | Approved | JOHN HAYES |
| HVAC-Final | 10/21/2021 | Approved | JOHN HAYES |
| PLUMBING-Final | 10/21/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 10/21/2021 | Approved | JOHN HAYES |