1601 S MAIN ST 90291

Certificate Information: 1601 S MAIN ST 90291

Application / Permit
21016-10000-03984
Plan Check / Job No.
B21LA02697
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
RENOVATION OF AN EXISTING OFFICE AND RESTRIPE EXISTING PARKING LOT (CORE AND SHELL ONLY).
Permit Issued
Issued on 4/29/2022
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 ERIC WONG
Corrections Issued 2/24/2021 ERIC WONG
Quality Review Completed 3/1/2021 PETER KIM
Green Plans Picked Up 3/4/2021 APPLICANT
Applicant returned to address corrections 5/14/2021 ERIC WONG
Applicant returned to address corrections 9/22/2021 ERIC WONG
Applicant returned to address corrections 3/23/2022 ERIC WONG
Plan Check Approved 3/25/2022 ERIC WONG
Issued 4/29/2022 APPLICANT
CofO in Progress 1/30/2025 FARHAD DADBIN
Permit Finaled 2/6/2025 DAVID TSAU
CofO Issued 2/6/2025 DAVID TSAU
Permit Finaled 2/6/2025 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/18/2021 ROSA SILVA
Specific Plan Cleared 3/19/2021 BINDU KANNAN
Green Code Cleared 6/10/2021 ERIC WONG
Comm Cor/Mini-Mall Cleared 6/16/2021 KENTON TRINH
Comm Cor/Mini-Mall Cleared 6/16/2021 KENTON TRINH
Prkng lot landscape/Water mgmt Cleared 6/16/2021 KENTON TRINH
DAS Clearance Cleared 7/22/2021 ERIC WONG
Low Impact Development Cleared 3/10/2022 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 3/24/2022 SAUL GARCIA

Contact Information

Architect Thoeny,, Bret Felix; Lic. No.: C21047 43 HALDEMAN ROAD      SANTA MONICA, CA 90402
Contractor J T M Construction Group Inc; Lic. No.: 956584-B 44 WEST 28TH STREET 11TH FLOOR      NEW YORK, NY 10001
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2022 Approved NICK LAROCCA
Grading Pre-Inspection 9/28/2022 Approved ALAN NOVAK
Deputy Grading 10/4/2022 Approved NICK LAROCCA
Deputy Drilled-In Anchors 10/6/2022 Conditional Approval GRANT WOODS
Deputy Grading 10/6/2022 Conditional Approval GRANT WOODS
Deputy Grading 10/7/2022 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 10/12/2022 Approved JEFF BYTHEWAY
Deputy Grading 10/12/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/12/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 10/13/2022 Conditional Approval GRANT WOODS
Deputy Grading 10/13/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 10/13/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 10/14/2022 Conditional Approval GRANT WOODS
Deputy Grading 10/14/2022 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 10/14/2022 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 10/18/2022 Conditional Approval DAVID TSAU
Excavation/Setback/Form/Re-Bar 10/18/2022 No Access for Inspection DAVID TSAU
Excavation/Setback/Form/Re-Bar 10/20/2022 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 10/27/2022 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 10/28/2022 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 10/31/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 10/31/2022 Approved SORIN CIRSTOIU
Deputy Grading 11/17/2022 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 11/22/2022 Partial Approval SORIN CIRSTOIU
Deputy Grading 11/23/2022 Approved NICK LAROCCA
Deputy Grading 11/28/2022 Conditional Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 12/8/2022 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 12/8/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 12/13/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 12/13/2022 Partial Inspection AMANUEL BERHE
Deputy Grading 12/22/2022 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 12/22/2022 Partial Approval SORIN CIRSTOIU
Deputy Grading 12/23/2022 Conditional Approval FARHAD DADBIN
Insulation 12/29/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 12/30/2022 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 1/10/2023 Conditional Approval SORIN CIRSTOIU
Reinforced Concrete Frame 1/19/2023 Approved FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 1/24/2023 Partial Inspection SORIN CIRSTOIU
T-Bar Ceiling 1/24/2023 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 1/25/2023 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 1/27/2023 Partial Approval SORIN CIRSTOIU
Insulation 1/27/2023 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 2/6/2023 Approved MICHAEL PETRUSKO
Deputy Grading 2/14/2023 Approved SORIN CIRSTOIU
Reinforced Concrete Frame 2/15/2023 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 2/16/2023 Partial Approval SORIN CIRSTOIU
Deputy Grading 2/21/2023 Conditional Approval AMANUEL BERHE
Reinforced Concrete Frame 3/1/2023 Partial Approval SORIN CIRSTOIU
Deputy Grading 3/3/2023 Approved FARHAD DADBIN
Deputy Grading 3/6/2023 Conditional Approval AMANUEL BERHE
Deputy Grading 3/7/2023 Conditional Approval SORIN CIRSTOIU
Deputy Grading 3/8/2023 Conditional Approval AMANUEL BERHE
Pre-Inspection 3/10/2023 Partial Inspection SORIN CIRSTOIU
Deputy Grading 3/22/2023 Conditional Approval AMANUEL BERHE
Light Gage Steel Frame 3/31/2023 Corrections Issued SORIN CIRSTOIU
Light Gage Steel Frame 3/31/2023 Not Ready for Inspection FARHAD DADBIN
Light Gage Steel Frame 4/7/2023 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 4/20/2023 Partial Approval SORIN CIRSTOIU
Pre-Inspection 5/9/2023 Corrections Issued SORIN CIRSTOIU
Pre-Inspection 7/12/2023 Not Ready for Inspection FARHAD DADBIN
Pre-Inspection 8/1/2023 Not Ready for Inspection FARHAD DADBIN
Pre-Inspection 8/3/2023 Partial Inspection SORIN CIRSTOIU
Special/Order Compliance 8/7/2023 Partial Inspection SORIN CIRSTOIU
Final 5/10/2024 Corrections Issued FARHAD DADBIN
Green Building Final 5/10/2024 Approved FARHAD DADBIN
Green Building Rough 5/10/2024 Approved FARHAD DADBIN
METHANE-Final 5/10/2024 Approved FARHAD DADBIN
METHANE-Rough 5/10/2024 Approved FARHAD DADBIN
Reinforced Masonry Frame 5/10/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 5/10/2024 Approved FARHAD DADBIN
Final 12/20/2024 Not Ready for Inspection FARHAD DADBIN
Final 1/10/2025 Not Ready for Inspection FARHAD DADBIN
Final 1/21/2025 OK to Issue CofO FARHAD DADBIN