1601 S MAIN ST 90291
Certificate Information: 1601 S MAIN ST 90291
- Application / Permit
- 21016-10000-03984
- Plan Check / Job No.
- B21LA02697
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- RENOVATION OF AN EXISTING OFFICE AND RESTRIPE EXISTING PARKING LOT (CORE AND SHELL ONLY).
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | ERIC WONG |
| Corrections Issued | 2/24/2021 | ERIC WONG |
| Quality Review Completed | 3/1/2021 | PETER KIM |
| Green Plans Picked Up | 3/4/2021 | APPLICANT |
| Applicant returned to address corrections | 5/14/2021 | ERIC WONG |
| Applicant returned to address corrections | 9/22/2021 | ERIC WONG |
| Applicant returned to address corrections | 3/23/2022 | ERIC WONG |
| Plan Check Approved | 3/25/2022 | ERIC WONG |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 1/30/2025 | FARHAD DADBIN |
| Permit Finaled | 2/6/2025 | DAVID TSAU |
| CofO Issued | 2/6/2025 | DAVID TSAU |
| Permit Finaled | 2/6/2025 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | ROSA SILVA |
| Specific Plan | Cleared | 3/19/2021 | BINDU KANNAN |
| Green Code | Cleared | 6/10/2021 | ERIC WONG |
| Comm Cor/Mini-Mall | Cleared | 6/16/2021 | KENTON TRINH |
| Comm Cor/Mini-Mall | Cleared | 6/16/2021 | KENTON TRINH |
| Prkng lot landscape/Water mgmt | Cleared | 6/16/2021 | KENTON TRINH |
| DAS Clearance | Cleared | 7/22/2021 | ERIC WONG |
| Low Impact Development | Cleared | 3/10/2022 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | SAUL GARCIA |
Contact Information
| Architect | Thoeny,, Bret Felix; Lic. No.: C21047 | 43 HALDEMAN ROAD SANTA MONICA, CA 90402 |
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2022 | Approved | NICK LAROCCA |
| Grading Pre-Inspection | 9/28/2022 | Approved | ALAN NOVAK |
| Deputy Grading | 10/4/2022 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 10/6/2022 | Conditional Approval | GRANT WOODS |
| Deputy Grading | 10/6/2022 | Conditional Approval | GRANT WOODS |
| Deputy Grading | 10/7/2022 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 10/12/2022 | Approved | JEFF BYTHEWAY |
| Deputy Grading | 10/12/2022 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 10/12/2022 | Approved | JEFF BYTHEWAY |
| Deputy Drilled-In Anchors | 10/13/2022 | Conditional Approval | GRANT WOODS |
| Deputy Grading | 10/13/2022 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 10/13/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/14/2022 | Conditional Approval | GRANT WOODS |
| Deputy Grading | 10/14/2022 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 10/14/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/18/2022 | Conditional Approval | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | No Access for Inspection | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 10/27/2022 | Partial Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 10/31/2022 | Approved | SORIN CIRSTOIU |
| Deputy Shotcrete | 10/31/2022 | Approved | SORIN CIRSTOIU |
| Deputy Grading | 11/17/2022 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Grading | 11/23/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 11/28/2022 | Conditional Approval | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 12/8/2022 | Partial Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 12/8/2022 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 12/13/2022 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 12/13/2022 | Partial Inspection | AMANUEL BERHE |
| Deputy Grading | 12/22/2022 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Grading | 12/23/2022 | Conditional Approval | FARHAD DADBIN |
| Insulation | 12/29/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 12/30/2022 | Approved | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 1/10/2023 | Conditional Approval | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 1/19/2023 | Approved | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Partial Inspection | SORIN CIRSTOIU |
| Light Gage Steel Frame | 1/24/2023 | Partial Inspection | SORIN CIRSTOIU |
| T-Bar Ceiling | 1/24/2023 | Partial Inspection | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 1/25/2023 | Partial Inspection | SORIN CIRSTOIU |
| Drywall Nailing | 1/27/2023 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 1/27/2023 | Partial Approval | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 2/6/2023 | Approved | MICHAEL PETRUSKO |
| Deputy Grading | 2/14/2023 | Approved | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 2/15/2023 | Partial Inspection | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 2/16/2023 | Partial Approval | SORIN CIRSTOIU |
| Deputy Grading | 2/21/2023 | Conditional Approval | AMANUEL BERHE |
| Reinforced Concrete Frame | 3/1/2023 | Partial Approval | SORIN CIRSTOIU |
| Deputy Grading | 3/3/2023 | Approved | FARHAD DADBIN |
| Deputy Grading | 3/6/2023 | Conditional Approval | AMANUEL BERHE |
| Deputy Grading | 3/7/2023 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Grading | 3/8/2023 | Conditional Approval | AMANUEL BERHE |
| Pre-Inspection | 3/10/2023 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Grading | 3/22/2023 | Conditional Approval | AMANUEL BERHE |
| Light Gage Steel Frame | 3/31/2023 | Corrections Issued | SORIN CIRSTOIU |
| Light Gage Steel Frame | 3/31/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 4/7/2023 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 4/20/2023 | Partial Approval | SORIN CIRSTOIU |
| Pre-Inspection | 5/9/2023 | Corrections Issued | SORIN CIRSTOIU |
| Pre-Inspection | 7/12/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 8/1/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 8/3/2023 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 8/7/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 5/10/2024 | Corrections Issued | FARHAD DADBIN |
| Green Building Final | 5/10/2024 | Approved | FARHAD DADBIN |
| Green Building Rough | 5/10/2024 | Approved | FARHAD DADBIN |
| METHANE-Final | 5/10/2024 | Approved | FARHAD DADBIN |
| METHANE-Rough | 5/10/2024 | Approved | FARHAD DADBIN |
| Reinforced Masonry Frame | 5/10/2024 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 5/10/2024 | Approved | FARHAD DADBIN |
| Final | 12/20/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 1/10/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 1/21/2025 | OK to Issue CofO | FARHAD DADBIN |