5701 N VANTAGE AVE 91607

Certificate Information: 5701 N VANTAGE AVE 91607

Application / Permit
21016-10000-03972
Plan Check / Job No.
B21LA02687
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE WITH ATTACHED PATIO COVER INTO A.D.U. PER STATE LAW. INCLUDES TWO NEW OPEN PARKING SPACES.
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
Issued on 9/17/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/17/2021 APPLICANT
Assigned to Plan Check Engineer 2/26/2021 LAWRENCE QUIRANTE
Corrections Issued 2/27/2021 LAWRENCE QUIRANTE
Plan Check Approved 8/25/2021 JESSE JIMENEZ
Building Plans Picked Up 8/27/2021 APPLICANT
Issued 9/17/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Permit Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/8/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/24/2021 ADRIAN CASTRO
Low Impact Development Cleared 8/4/2021 MITESH PATEL

Contact Information

Contractor Cal-Western Construction; Lic. No.: 592405-B 12121 BEATRICE STREET      CULVER CITY, CA 90230
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2021 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/9/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 11/9/2021 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 11/24/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/6/2021 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/6/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 12/6/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/6/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/15/2021 Approved CHRISTOPHE COCHRAN
HVAC-Rough 12/15/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/15/2021 Partial Approval CHRISTOPHE COCHRAN
Insulation 12/21/2021 Approved JACK KARGODORIAN
Drywall Nailing 12/23/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/23/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/29/2021 Approved JOHN HAYES
Shower Pan 12/29/2021 Approved JOHN HAYES
ELECTRICAL-Final 2/9/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 2/9/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Final 2/9/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 2/28/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 2/28/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 2/28/2022 Approved CHRISTOPHE COCHRAN