629 N ROSEMONT AVE 90026

Certificate Information: 629 N ROSEMONT AVE 90026

Application / Permit
21016-10000-03968
Plan Check / Job No.
B21LA02685
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) 1-STORY SFD AT FRONT OF LOT. INCLUDES REMOVAL AND REFRAME OF ROOF.
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
Permit Finaled on 9/7/2022

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 2/26/2021 LAWRENCE QUIRANTE
Corrections Issued 2/27/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/8/2021 AUNG SOE
Plan Check Approved 9/30/2021 SAMUEL GONZALEZ
Issued 10/12/2021 APPLICANT
Building Plans Picked Up 10/20/2021 APPLICANT
Permit Finaled 9/6/2022 FREDDIE RIVERA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2021 JEANIE LAM
Low Impact Development Cleared 9/7/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/21/2021 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 12/28/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 1/11/2022 Partial Inspection AMY COLIN
BUILDING-Rough-Frame 4/22/2022 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 4/22/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 4/22/2022 Approved FREDDIE RIVERA
HVAC-Rough 4/22/2022 Partial Approval FREDDIE RIVERA
MERV13>=Rough 4/22/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 4/22/2022 Corrections Issued FREDDIE RIVERA
Drywall Nailing 5/9/2022 Approved FREDDIE RIVERA
HVAC-Rough 5/9/2022 Approved FREDDIE RIVERA
Insulation 5/9/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/9/2022 Approved FREDDIE RIVERA
PLUMBING-Rough 5/9/2022 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/17/2022 Approved FREDDIE RIVERA
HVAC-Final 7/27/2022 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/25/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/25/2022 Approved FREDDIE RIVERA
Final 8/25/2022 Corrections Issued FREDDIE RIVERA
HVAC-Final 8/25/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Final 8/25/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 8/25/2022 Approved FREDDIE RIVERA
Service/Power Release 8/25/2022 Approved FREDDIE RIVERA
Smoke Detectors 8/25/2022 Approved FREDDIE RIVERA
ELECTRICAL-Final 9/6/2022 Approved FREDDIE RIVERA
Final 9/6/2022 Permit Finaled FREDDIE RIVERA
HVAC-Final 9/6/2022 Approved FREDDIE RIVERA
MERV13>=Final 9/6/2022 Approved FREDDIE RIVERA
PLUMBING-Final 9/6/2022 Approved FREDDIE RIVERA
Service/Power Release 9/6/2022 Approved FREDDIE RIVERA