604 E ROSE AVE 90291
Certificate Information: 604 E ROSE AVE 90291
- Application / Permit
- 21016-10000-03899
- Plan Check / Job No.
- B21LA02632
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Clinic
- Work Description
- Interior and exterior renovation of an existing medical office building at first and second floors, including new walls, ceiling systems, floor layout, ADA restrooms, and finishes. Change of use of a portion of first floor to pharmacy. Resurface and relayout a portion of parking lot, including new ADA and bicycle parking spaces. Elevator will be a part of the OSHPO-3 clinic at the second floor.
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | HELEN NGUYEN |
| Corrections Issued | 2/23/2021 | HELEN NGUYEN |
| Quality Review Completed | 2/24/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 3/23/2021 | APPLICANT |
| Green Plans Picked Up | 5/27/2021 | APPLICANT |
| Applicant returned to address corrections | 6/3/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/8/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 8/4/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/21/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/23/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/27/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/28/2021 | HELEN NGUYEN |
| Plan Check Approved | 10/5/2021 | HELEN NGUYEN |
| Issued | 10/18/2021 | APPLICANT |
| TCO Issued (Expire Date: 02-11-2023) | 8/15/2022 | DAVID TSAU |
| TCO Issued (Expire Date: 09-02-2023) | 3/6/2023 | DAVID TSAU |
| TCO Issued (Expire Date: 03-19-2024) | 9/21/2023 | DAVID TSAU |
| CofO in Progress | 2/26/2025 | FARHAD DADBIN |
| Permit Finaled | 3/4/2025 | DAVID TSAU |
| CofO Issued | 3/4/2025 | DAVID TSAU |
| Permit Finaled | 3/4/2025 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 5/13/2021 | AARON COSTA |
| Low Impact Development | Cleared | 6/17/2021 | MARTIN FRAGOSO |
| DAS Clearance | Cleared | 6/28/2021 | HELEN NGUYEN |
| Coastal Zone | Cleared | 7/22/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/4/2021 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 8/6/2021 | IRA BROWN |
Contact Information
| Architect | Tyner,, Russel Edward; Lic. No.: C14979 | 2630 SEPULVEDA BLVD TORRANCE, CA 90505 |
| Contractor | Driver S P G Llc; Lic. No.: 960119-B | 468 NORTH ROSEMEAD BLVD PASADENA, CA 91107 |
| Engineer | Khamsi,, Ali; Lic. No.: C74768 | 713 POINSETTIA AVE CORONA DEL MAR, CA 92625 |
| Engineer | Stewart,, Joseph Eugene; Lic. No.: S3065 | 4117 MEADOW LARK DR CALABASAS, CA 91302 |
| Landscape Architect | Van, Sooy, Scott; Lic. No.: LA5505 | 9017 DICKS STREET WEST HOLLYWOOD, CA 90069 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/21/2021 | Approved | NICK LAROCCA |
| Pre-Inspection | 11/2/2021 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 11/19/2021 | Corrections Issued | NICK LAROCCA |
| Deputy Other (see comments) | 11/22/2021 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 11/22/2021 | Conditional Approval | JOHN DODGE |
| Green Building Rough | 12/16/2021 | Approved | JOEY BUCHANAN |
| Wood Frame | 12/16/2021 | Partial Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 1/10/2022 | Partial Approval | JOHN DODGE |
| Footing/Foundation/Slab | 1/18/2022 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 1/20/2022 | Partial Approval | DERRICK SPENCER |
| Insulation | 1/21/2022 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 1/26/2022 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | JOHN DODGE |
| Footing/Foundation/Slab | 2/1/2022 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 2/9/2022 | Not Ready for Inspection | JOHN DODGE |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 2/9/2022 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 2/14/2022 | Partial Approval | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Not Ready for Inspection | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Partial Approval | GRANT WOODS |
| Wood Frame | 2/16/2022 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 2/23/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 2/23/2022 | Partial Inspection | GRANT WOODS |
| Light Gage Steel Frame | 2/28/2022 | Partial Approval | NICK LAROCCA |
| Wood Frame | 2/28/2022 | Partial Inspection | NICK LAROCCA |
| Wood Frame | 3/2/2022 | Partial Approval | JOHN DODGE |
| Wood Frame | 3/8/2022 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 3/9/2022 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 3/24/2022 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 4/13/2022 | Partial Approval | JOHN DODGE |
| Pre-Inspection | 5/5/2022 | Approved | JOHN DODGE |
| Wood Frame | 5/5/2022 | Not Ready for Inspection | JOHN DODGE |
| Light Gage Steel Frame | 5/9/2022 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 5/9/2022 | Partial Approval | JOHN DODGE |
| Light Gage Steel Frame | 5/12/2022 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 5/18/2022 | Approved | JOHN DODGE |
| Insulation | 5/26/2022 | Approved | JOHN DODGE |
| T-Bar Ceiling | 6/2/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| T-Bar Ceiling | 6/3/2022 | Partial Approval | SORIN CIRSTOIU |
| T-Bar Ceiling | 6/7/2022 | No Access for Inspection | GRANT WOODS |
| T-Bar Ceiling | 6/9/2022 | Partial Approval | GRANT WOODS |
| T-Bar Ceiling | 6/17/2022 | Partial Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 6/23/2022 | Partial Approval | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 7/6/2022 | Partial Approval | GRANT WOODS |
| Interior/Exterior Lathing | 7/6/2022 | Partial Approval | GRANT WOODS |
| Green Building Final | 7/13/2022 | Approved | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 1/18/2023 | Partial Inspection | GRANT WOODS |
| Special/Order Compliance | 8/9/2023 | Partial Approval | FARHAD DADBIN |
| Special/Order Compliance | 2/28/2024 | Partial Approval | FARHAD DADBIN |
| Final | 2/26/2025 | OK to Issue CofO | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 2/26/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 2/26/2025 | Approved | FARHAD DADBIN |