3582 N DIVISION ST 90065

Certificate Information: 3582 N DIVISION ST 90065

Application / Permit
21016-10000-03879
Plan Check / Job No.
B21LA02592
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel - kitchen, master suite. Replace all windows and doors.
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
Permit Finaled on 10/29/2021

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 HERNAN ARREOLA
Corrections Issued 2/17/2021 HERNAN ARREOLA
Plan Check Approved 3/2/2021 HERNAN ARREOLA
Issued 3/12/2021 APPLICANT
Permit Finaled 10/28/2021 OSVALDO PARAMO

Permit Application Clearance Information

Specific Plan Cleared 2/18/2021 DYLAN LAWRENCE

Contact Information

Contractor Casa Bonita Builders Inc; Lic. No.: 993435-B 1866 E CALAVERAS ST      ALTADENA, CA 91001
Engineer Song,, Zhenyu Michael; Lic. No.: NA5266       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/9/2021 Partial Approval DAVID FEILER
Deputy Drilled-In Anchors 6/15/2021 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 7/1/2021 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 7/1/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 7/1/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 7/9/2021 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 7/9/2021 Partial Approval OSVALDO PARAMO
HVAC-Rough 7/9/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 7/9/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 7/12/2021 Partial Approval OSVALDO PARAMO
Shower Pan 7/12/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 7/26/2021 Approved BRIAN SULLIVAN
Insulation 7/29/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/10/2021 Approved CALEB MEISTER
Drywall Nailing 8/10/2021 Conditional Approval CALEB MEISTER
Drywall Nailing 8/12/2021 Approved OSVALDO PARAMO
Final 10/28/2021 Permit Finaled OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/28/2021 Approved OSVALDO PARAMO