817 S MANHATTAN PL 90005
Certificate Information: 817 S MANHATTAN PL 90005
- Application / Permit
- 21016-10000-03772
- Plan Check / Job No.
- B21LA02585
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install New Steel Cantilever columns and grade beams
- Permit Issued
- Issued on 5/4/2021
- Issuing Office
- Current Status
- CofC Issued on 9/25/2023
Permit Application Status History
| Submitted | 2/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | HANS SANTIAGO |
| Corrections Issued | 2/22/2021 | HANS SANTIAGO |
| Quality Review Completed | 3/1/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/30/2021 | HANS SANTIAGO |
| Plan Check Approved | 4/28/2021 | ANDREW SANTIAGO |
| Issued | 5/4/2021 | APPLICANT |
| OK for CofC | 9/14/2023 | VAHE KELEDJIAN |
| CofC Issued | 9/25/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/29/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Mae Cm Services Inc; Lic. No.: 886471-B | , |
| Engineer | Standley,, Craig Erick; Lic. No.: NA87675 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 5/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 5/26/2021 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 5/28/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 6/4/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/8/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/9/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 6/9/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/15/2021 | Approved | MARK FERRARI |
| Final | 12/7/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Final | 9/14/2023 | OK for CofC | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 9/14/2023 | Approved | VAHE KELEDJIAN |