330 S ALAMEDA ST 90013

Certificate Information: 330 S ALAMEDA ST 90013

Application / Permit
21016-10000-03696
Plan Check / Job No.
B21LA02522
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(21) Motion Picture Studio
Work Description
TENANT IMPROVEMENT TO (E) MOTION PICTURE PRODUCTION FACILITY ON FIRST AND SECOND FLOORS FOR NEW TIERED-SEATING SCREENING ROOM, RESTROOMS OFFICES, AND ROOFTOP EQUIPMENT
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
Permit Finaled on 10/23/2024

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 LAMAR DAVIS
Corrections Issued 2/23/2021 LAMAR DAVIS
Quality Review Completed 3/11/2021 WING SUEN
Building Plans Picked Up 3/16/2021 APPLICANT
Disabled Access Plans Picked Up 3/25/2021 APPLICANT
Green Plans Picked Up 5/13/2021 APPLICANT
Plan Check Approved 5/25/2021 LAMAR DAVIS
Issued 5/26/2021 APPLICANT
Permit Finaled 10/23/2024 RONALD JIMENEZ

Permit Application Clearance Information

DAS Clearance Cleared 5/4/2021 EDDIE GARIN
Green Code Cleared 5/13/2021 AARON COSTA

Contact Information

Architect Korchien,, Richard; Lic. No.: C6836 8530 VENICE BLVD      LOS ANGELES, CA 90034
Contractor Turelk Inc; Lic. No.: 372562-B P O BOX 93101      LONG BEACH, CA 90809
Engineer Blackman,, Brent Allen; Lic. No.: S4635 855 N DOUGLAS ST      EL SEGUNDO, CA 90245

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 6/14/2021 Partial Inspection JONATHAN QUACH
Insulation 6/22/2021 Approved LANNY MERRICK
Drywall Nailing 6/23/2021 Approved LANNY MERRICK
Insulation 7/8/2021 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval LANNY MERRICK
Deputy Drilled-In Anchors 7/22/2021 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 7/26/2021 Approved LANNY MERRICK
Deputy Reinf. Concrete 7/28/2021 Conditional Approval LANNY MERRICK
Drywall Nailing 7/28/2021 Not Ready for Inspection LANNY MERRICK
Drywall Nailing 7/29/2021 Not Ready for Inspection LANNY MERRICK
Light Gage Steel Frame 8/13/2021 Approved LANNY MERRICK
Deputy Drilled-In Anchors 9/7/2021 Conditional Approval LANNY MERRICK
T-Bar Ceiling 9/7/2021 Approved LANNY MERRICK
T-Bar Ceiling 9/8/2021 Approved LANNY MERRICK
Light Gage Steel Frame 9/13/2021 Conditional Approval DANIEL COLLINS
Final 11/24/2021 Not Ready for Inspection MARK FERRARI
Green Building Final 11/24/2021 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Not Ready MARK FERRARI
Smoke Detectors 11/24/2021 Not Ready for Inspection MARK FERRARI
Final 11/29/2021 Corrections Issued MARK FERRARI
Green Building Final 11/29/2021 Approved MARK FERRARI
Pre-Inspection 11/29/2021 Not Ready for Inspection MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 11/29/2021 Approved MARK FERRARI
Special/Order Compliance 11/29/2021 Not Ready for Inspection MARK FERRARI
Special/Order Compliance 2/17/2022 Partial Inspection MARK FERRARI
Final 1/29/2024 Partial Approval RICARDO ROBLES
Final 10/23/2024 Permit Finaled RONALD JIMENEZ