15301 W VENTURA BLVD 91403

Certificate Information: 15301 W VENTURA BLVD 91403

Application / Permit
21016-10000-03673
Plan Check / Job No.
B21LA02494
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
eplan. New equipment pads for Tesla EV V3 Supercharging stations & parking re-stripe
Permit Issued
Issued on 3/24/2022
Issuing Office
Current Status
Permit Finaled on 11/14/2022

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 PRANITA SHAH
Corrections Issued 4/5/2021 PRANITA SHAH
Quality Review Completed 4/9/2021 MICHAEL PEREZ
Applicant returned to address corrections 5/7/2021 PRANITA SHAH
Applicant returned to address corrections 9/22/2021 PRANITA SHAH
Applicant returned to address corrections 9/29/2021 PRANITA SHAH
Plan Check Approved 10/14/2021 PRANITA SHAH
No Progress 10/14/2021 PRANITA SHAH
Plan Check Approved 10/27/2021 PRANITA SHAH
Issued 3/24/2022 APPLICANT
Permit Finaled 11/14/2022 ANDREW DORSO

Permit Application Clearance Information

DAS Clearance Cleared 6/10/2021 PRANITA SHAH

Contact Information

Architect Maresca,, Christopher Thomas; Lic. No.: C32449 2204 ALBATROSS ST      SAN DIEGO, CA 92101
Contractor Potential Electrical Design Services Inc; Lic. No.: 996042-A 5666 LA JOLLA BLVD #242      LA JOLLA, CA 92037
Engineer Kim,, Yoo Jin; Lic. No.: S5771 129 GERBERA STREET      DANVILLE, CA 94506

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2022 Partial Inspection DANIEL VARNUM
Footing/Foundation/Slab 5/25/2022 Approved DANIEL VARNUM
Deputy Reinf. Concrete 5/26/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/1/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/2/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/13/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/14/2022 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 6/22/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 6/23/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/26/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 9/13/2022 Partial Inspection DANIEL VARNUM
Final 10/24/2022 Partial Inspection JEFFREY FULTON
Reinforced Concrete Frame 10/24/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 10/24/2022 Not Ready for Inspection JEFFREY FULTON
Final 10/31/2022 Corrections Issued ANDREW DORSO
Reinforced Concrete Frame 10/31/2022 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved ANDREW DORSO
Smoke Detectors 10/31/2022 Approved ANDREW DORSO
Final 11/14/2022 Permit Finaled ANDREW DORSO