15301 W VENTURA BLVD 91403
Certificate Information: 15301 W VENTURA BLVD 91403
- Application / Permit
- 21016-10000-03673
- Plan Check / Job No.
- B21LA02494
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- eplan. New equipment pads for Tesla EV V3 Supercharging stations & parking re-stripe
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/14/2022
Permit Application Status History
| Submitted | 2/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | PRANITA SHAH |
| Corrections Issued | 4/5/2021 | PRANITA SHAH |
| Quality Review Completed | 4/9/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 5/7/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 9/22/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 9/29/2021 | PRANITA SHAH |
| Plan Check Approved | 10/14/2021 | PRANITA SHAH |
| No Progress | 10/14/2021 | PRANITA SHAH |
| Plan Check Approved | 10/27/2021 | PRANITA SHAH |
| Issued | 3/24/2022 | APPLICANT |
| Permit Finaled | 11/14/2022 | ANDREW DORSO |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/10/2021 | PRANITA SHAH |
Contact Information
| Architect | Maresca,, Christopher Thomas; Lic. No.: C32449 | 2204 ALBATROSS ST SAN DIEGO, CA 92101 |
| Contractor | Potential Electrical Design Services Inc; Lic. No.: 996042-A | 5666 LA JOLLA BLVD #242 LA JOLLA, CA 92037 |
| Engineer | Kim,, Yoo Jin; Lic. No.: S5771 | 129 GERBERA STREET DANVILLE, CA 94506 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2022 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 5/25/2022 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 5/26/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 6/2/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 6/13/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 6/14/2022 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 6/22/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 6/23/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 8/26/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 9/13/2022 | Partial Inspection | DANIEL VARNUM |
| Final | 10/24/2022 | Partial Inspection | JEFFREY FULTON |
| Reinforced Concrete Frame | 10/24/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 10/24/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 10/31/2022 | Corrections Issued | ANDREW DORSO |
| Reinforced Concrete Frame | 10/31/2022 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 10/31/2022 | Approved | ANDREW DORSO |
| Final | 11/14/2022 | Permit Finaled | ANDREW DORSO |