13961 W OXNARD ST 91401
Certificate Information: 13961 W OXNARD ST 91401
- Application / Permit
- 21016-10000-03495
- Plan Check / Job No.
- B21LA02336
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (2) 2-BAY ORDINARY MOMENT FRAMES WITH GRADE BEAMS.
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofC Issued on 12/16/2021
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | HANS SANTIAGO |
| Corrections Issued | 3/8/2021 | HANS SANTIAGO |
| Quality Review Completed | 3/8/2021 | SAI KHUM |
| Applicant returned to address corrections | 3/10/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 4/13/2021 | HANS SANTIAGO |
| Plan Check Approved | 5/17/2021 | ANDREW SANTIAGO |
| Issued | 6/10/2021 | APPLICANT |
| OK for CofC | 10/26/2021 | KENNETH ROBERTS |
| CofC Issued | 12/16/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 3/17/2021 | ANDREW SANTIAGO |
| Tenant Habitability Plan | Cleared | 6/10/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 6/29/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/6/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 7/13/2021 | No Access for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/19/2021 | No Access for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 7/23/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 7/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | JOE VELASQUEZ |
| Drywall Nailing | 8/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 8/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Drywall Nailing | 8/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 8/31/2021 | No Access for Inspection | JOE VELASQUEZ |
| Drywall Nailing | 8/31/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/31/2021 | Corrections Issued | JOE VELASQUEZ |
| Drywall Nailing | 9/17/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Conditional Approval | JOE VELASQUEZ |
| Wood Frame | 9/17/2021 | Conditional Approval | JOE VELASQUEZ |
| Interior/Exterior Lathing | 10/7/2021 | Approved | DANIEL VARNUM |
| Final | 10/22/2021 | Partial Approval | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/22/2021 | Approved | KENNETH ROBERTS |
| Final | 10/26/2021 | OK for CofC | KENNETH ROBERTS |