5062 W BEVERLY BLVD 90004
Certificate Information: 5062 W BEVERLY BLVD 90004
- Application / Permit
- 21016-10000-03362
- Plan Check / Job No.
- B21LA02214
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING GARAGE DETACHED TO CONVERT INTO AN ADU.
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- CofO Issued on 3/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 2/16/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 5/17/2021 | CRISTINA SALAZAR |
| Plan Check Approved | 6/15/2021 | TSE MING HUANG |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| Issued | 6/29/2021 | APPLICANT |
| CofO in Progress | 12/21/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 12/21/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 3/3/2023 | DANIEL ORRANTE |
| CofO Issued | 3/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/11/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 3/16/2021 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 4/27/2021 | MATTHEW CRAIG |
| HPOZ | Cleared | 5/5/2021 | LYDIA CHAPMAN |
Contact Information
| Contractor | South Land Remodeling Inc; Lic. No.: 901842-B | 10770 DES MOINES AVE NORTHRIDGE, CA 91326 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/22/2021 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 8/3/2021 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 8/3/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 10/5/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 10/5/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/5/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/6/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Underground Mechanical | 10/6/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 10/6/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 10/19/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 10/19/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Not Required | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| Final | 12/15/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| METHANE-Final | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 12/15/2021 | Approved | ARTHUR SARGSYAN |
| Final | 12/20/2021 | OK to Issue CofO | ARTHUR SARGSYAN |